NPRR #1128 · Revision Request

NPRR1128  Allow FFR Procurement up to FFR Limit Without Proration

Approved sponsor Hunt Energy Network posted 2022-03-25 ercot.com
  1. PRS Oct 13 '22
  2. TAC Oct 26 '22
  3. BOARD Dec 20 '22
  4. PUCT Jan 26 '23
ReasonMarket efficiencies or enhancements
Created2022-04-14
Approved2023-01-26
Sections Affected
3.164.4.7.2.1and 4.4.7.2.3
Summary
This Nodal Protocol Revision Request (NPRR) sets a -$0.01 per MW lower Ancillary Service Offer floor for Fast Frequency Response (FFR) Responsive Reserve (RRS) rather than for other RRS categories, thereby allowing, depending on relative Ancillary Service Offers, FFR procurement up to the current FFR limit without proration with other RRS categories in the Ancillary Service procurement process.
Timeline