NPRR #1118 · Revision Request

NPRR1118  Clarifications to the OSA Process

Approved sponsor ERCOT posted 2022-01-25 ercot.com
ReasonAddresses current operational issues / Market efficiencies or enhancements / Regulatory requirements
Created2022-02-09
Approved2022-11-03
Sections Affected
3.1.6.9 and 5.6.5.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the Outage Schedule Adjustment (OSA) process based on lessons learned from performing this process during 2021, as well as other factors. The first set of changes improves the terminology and clarifies the process for issuing Advanced Action Notices (AANs) and OSAs. The second set of changes clarify offer submission and Reliability Unit Commitment (RUC) procedures after an OSA is issued.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Aug 11 '22PRS To recommend approval of NPRR1118 as amended by the 6/13/22 ERCOT comments as revised by PRSPassed
Ballots
DateBodyResultYesNoAbstain
Sep 15 '22 PRS Motion Carries 7 0 0 xls
Aug 11 '22 PRS Motion Carries 7 0 0 xls
Aug 10 '22 ROS Motion Carries 7.5 0 0 xls
Aug 3 '22 WMS Motion Carries 7.5 0 2 xls
Mar 3 '22 ROS Motion Carries 7.5 0 1 xls
Feb 9 '22 PRS Motion Carries 7 0 0 xls
Documents 21
NameTypePostedClassification
1118NPRR-01 Clarifications to the OSA Process 012522 docx Jan 25 '22 Revision Request
1118NPRR-02 Impact Analysis 012522 docx Jan 25 '22 Staff Report
1118NPRR-03 PRS Ballot 020922 xls Feb 14 '22 Revision Request Ballot
1118NPRR-04 PRS Report 020922 docx Feb 14 '22 Committee Report
1118NPRR-05 WMS Ballot 030222 xls Mar 7 '22 Revision Request Ballot
1118NPRR-06 WMS Comments 030722 docx Mar 7 '22 Revision Request Comments
1118NPRR-07 ROS Ballot 030322 xls Mar 7 '22 Revision Request Ballot
1118NPRR-08 ROS Comments 030722 docx Mar 7 '22 Revision Request Comments
1118NPRR-09 ERCOT Comments 061322 docx Jun 13 '22 Revision Request Comments
1118NPRR-10 WMS Ballot 080322 xls Aug 5 '22 Revision Request Ballot
1118NPRR-11 WMS Comments 080522 doc Aug 5 '22 Revision Request Comments
1118NPRR-12 ROS Ballot 081022 xls Aug 11 '22 Revision Request Ballot
1118NPRR-13 ROS Comments 081122 docx Aug 11 '22 Revision Request Comments
1118NPRR-14 PRS Ballot 081122 xls Aug 16 '22 Revision Request Ballot
1118NPRR-15 PRS Report 081122 docx Aug 16 '22 Committee Report
1118NPRR-16 PRS Ballot 091522 xls Sep 19 '22 Revision Request Ballot
1118NPRR-17 PRS Report 091522 docx Sep 19 '22 Committee Report
1118NPRR-18 TAC Ballot 092822 xls Sep 29 '22 Revision Request Ballot
1118NPRR-19 TAC Report 092822 docx Sep 29 '22 Committee Report
1118NPRR-20 Board Report 101822 docx Oct 19 '22 Committee Report
1118NPRR-21 PUCT Report 110322 docx Nov 3 '22 Committee Report
Meetings That Took It Up 28
DateMeetingCommitteeStatus
Oct 18 '22 Board of Directors Meeting BOARD Concluded
Sep 28 '22 TAC Meeting TAC Concluded
Sep 15 '22 PRS Meeting PRS Concluded
Aug 11 '22 PRS Meeting PRS Concluded
Aug 10 '22 ROS Meeting ROS Concluded
Aug 3 '22 WMS Meeting WMS Concluded
Jul 26 '22 WMWG Meeting by Webex Only WMWG Concluded
Jul 13 '22 PRS Meeting PRS Concluded
Jun 23 '22 OWG Meeting by Webex Only OWG Concluded
Jun 9 '22 PRS Meeting PRS Concluded
Jun 2 '22 ROS Meeting ROS Concluded
Jun 1 '22 WMS Meeting WMS Concluded
May 20 '22 WMWG Meeting by Webex Only WMWG Concluded
May 19 '22 OWG Meeting by Webex Only OWG Concluded
May 11 '22 PRS Meeting PRS Concluded
May 5 '22 ROS Meeting ROS Concluded
May 4 '22 WMS Meeting WMS Concluded
Apr 22 '22 WMWG Meeting by Webex Only WMWG Concluded
Apr 21 '22 OWG Meeting by Webex Only OWG Concluded
Apr 14 '22 PRS Meeting PRS Concluded
Apr 7 '22 ROS Meeting ROS Concluded
Apr 6 '22 WMS Meeting WMS Concluded
Mar 25 '22 WMWG Meeting by Webex Only WMWG Concluded
Mar 24 '22 OWG Meeting by Webex Only OWG Concluded
Mar 9 '22 PRS Meeting by Webex Only PRS Concluded
Mar 3 '22 ROS Meeting by Webex Only ROS Concluded
Mar 2 '22 WMS Meeting by Webex Only WMS Concluded
Feb 9 '22 PRS Meeting by Webex Only PRS Concluded