NPRR #1088 · Revision Request

NPRR1088  Applying Forward Adjustment Factors to Forward Market Positions and Un-applying Forward Adjustment Factors to Prior Market Positions

Rejected sponsor Grand Oak Capital Partners, LP posted 2021-07-26 ercot.com
ReasonAddresses current operational issues; meets Strategic goals; market efficiencies or enhancements
Created2021-08-12
Rejected2022-06-09
Sections Affected
4.4.10 and 16.11.4.3
Summary
This Nodal Protocol Revision Request (NPRR) removes the Real-Time Forward Adjustment Factor (RFAF) and the Day-Ahead Forward Adjustment Factor (DFAF) from being applied to prior market positions and instead applies the RFAF and DFAF to ongoing market positions.
Action Log 2 milestones
Ballots
DateBodyResultYesNoAbstain
Jun 9 '22 PRS Motion Carries 7 0 0 xls
Jun 1 '22 WMS Motion Carries 7 0 2 xls
Aug 12 '21 PRS Motion Carries 7 0 1 xls
Documents 8
NameTypePostedClassification
1088NPRR-01 Applying Forward Adjustment Factors to Forward Market Positions and Un-applying Forward Adjustment Factors to Prior Market Positions 072621 docx Jul 26 '21 Revision Request
1088NPRR-02 ERCOT Comments 080621 docx Aug 6 '21 Revision Request Comments
1088NPRR-03 PRS Ballot 081221 xls Aug 26 '21 Revision Request Ballot
1088NPRR-04 PRS Report 081221 docx Aug 17 '21 Committee Report
1088NPRR-05 WMS Comments 090321 doc Sep 3 '21 Revision Request Comments
1088NPRR-06 WMS Comments 060622 docx Jun 6 '22 Revision Request Comments
1088NPRR-07 PRS Ballot 060922 xls Jun 14 '22 Revision Request Ballot
1088NPRR-08 PRS Report 060922 docx Jun 14 '22 Committee Report
Meetings That Took It Up 26
DateMeetingCommitteeStatus
Jun 27 '22 TAC Meeting TAC Concluded
Jun 9 '22 PRS Meeting PRS Concluded
Jun 1 '22 WMS Meeting WMS Concluded
May 11 '22 PRS Meeting PRS Concluded
May 4 '22 WMS Meeting WMS Concluded
Apr 14 '22 PRS Meeting PRS Concluded
Apr 6 '22 WMS Meeting WMS Concluded
Mar 9 '22 PRS Meeting by Webex Only PRS Concluded
Mar 2 '22 WMS Meeting by Webex Only WMS Concluded
Feb 9 '22 PRS Meeting by Webex Only PRS Concluded
Feb 2 '22 WMS Meeting by Webex Only WMS Concluded
Jan 13 '22 PRS Meeting by Webex Only PRS Concluded
Jan 5 '22 WMS Meeting by Webex Only WMS Concluded
Dec 14 '21 PRS Meeting by Webex Only PRS Concluded
Dec 1 '21 WMS Meeting by Webex Only WMS Concluded
Nov 11 '21 CWG/MCWG Meeting by Webex Only CREDITWG Concluded
Nov 10 '21 PRS Meeting by Webex Only PRS Concluded
Nov 3 '21 WMS Meeting by Webex Only WMS Concluded
Oct 20 '21 CWG/MCWG Meeting by Webex Only CREDITWG Concluded
Oct 14 '21 PRS Meeting by Webex Only PRS Concluded
Oct 6 '21 WMS Meeting by Webex Only WMS Concluded
Sep 21 '21 CWG/MCWG Meeting by Webex Only CREDITWG Concluded
Sep 16 '21 PRS Meeting by Webex Only PRS Concluded
Sep 1 '21 WMS Meeting by Webex Only WMS Concluded
Aug 18 '21 CWG/MCWG Meeting by Webex Only CREDITWG Concluded
Aug 12 '21 PRS Meeting by Webex Only PRS Concluded