NPRR #107 · Revision Request
NPRR107 Nodal Emergency Interruptible Load Service (EILS)
ReasonEILS is required by PUC Subst. R. 25.507, Electric Reliability Council of Texas (ERCOT) Emergency Interruptible Load Service (EILS).
Created2008-03-20
Approved2008-07-15
Sections Affected
Section 2Definitions and Acronyms; Section 3.14Contracts for Reliability Resources; Section 3.14.3Emergency Interruptible Load Service (EILS) (New); Section 6.5.8.1Deployment of Emergency Interruptible Load Service (EILS) (New); Section 6.5.9Emergency Operations; Section 6.5.9.4Emergency Electric Curtailment Plan Section; 6.5.9.7Emergency Interruptible Load Service (EILS) (New); Section 6.6.11Emergency Interruptible Load Service (EILS) Settlement (New); Section 8.1.3Emergency Interruptible Load Service (EILS) Performance Criteria and Testing Requirements (New); Section 9.14.5Resettlement of Emergency Interruptible Load Service (New); (subsequent subsections in Section 9.14 renumbered); Section 16.13Registration of Emergency Interruptible Load Service (EILS) Resources (New); Section 22 -- Attachment 22KStandard Form Emergency Interruptible Load Service Agreement (Reformatted)
Summary
This NPRR modifies the ERCOT Nodal Protocols to transition the EILS to the Nodal market. EILS is deployed during an Emergency Electric Curtailment Plan (EECP), after all available Generation and Loads acting as Resources (LaaRs) have been deployed. This NPRR makes no material changes to EILS as it currently is defined in the Zonal Protocols. In various cases, certain language has been modified slightly to enhance clarity.
Action Log 5 milestones
-
Mar 20
PRSReferred→ Review of NPRR107 by TPTF
-
May 22
PRSRecommended for Approval→ Review of Impact Analysis and Recommendation Report.
-
Jun 26
TACRecommended for Approval→ ERCOT Board consideration.
-
Jul 15
BOARDApproved
-
Jun 19
PRSRecommended for Approval→ Consideration of NPRR107 by TAC.
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| May 22 '08 | PRS | To recommend approval of NPRR107 as revised by TPTF comments. The motion passed with one opposing vote from the Independent Power Marketer (IPM) Market Segment and four abstentions from the Municipally Owned Utility (MOU), Investor Owned Utility (IOU), Independent Generator (IG), IPM, and Independent Retail Electric Provider (IREP) Market Segments. All Market Segments were present for the vote. | Passed |
| Jun 19 '08 | PRS | To recommend approval of NPRR107 as revised by ERCOT Staff 061808 comments, endorse the Impact Analysis and Recommendation Report, and forward the documents to TAC. | Passed |
Documents 12
| Name | Type | Posted | Classification |
|---|---|---|---|
| 107NPRR-01 Nodal Emergency Interruptible Load Service (EILS) 022 | doc | Feb 29 '08 | Revision Request |
| 107NPRR-02 PRS Action Report 032008 | doc | Mar 25 '08 | Committee Report |
| 107NPRR-03 ERCOT Staff Comments 041608 | doc | Apr 16 '08 | Revision Request Comments |
| 107NPRR-04 TPTF Voting Ballot 050608 | xls | May 8 '08 | Revision Request Ballot |
| 107NPRR-05 TPTF Comments 050908 | doc | May 9 '08 | Revision Request Comments |
| 107NPRR-06 PRS Recommendation Report 052208 | doc | May 28 '08 | Committee Report |
| 107NPRR-07 Preliminary Impact Analysis Report 061308 | doc | Jun 13 '08 | Staff Report |
| 107NPRR-08 ERCOT Staff Comments 061808 | doc | Jun 18 '08 | Revision Request Comments |
| 107NPRR-09 Impact Analysis Report 061808 | doc | Jun 18 '08 | Staff Report |
| 107NPRR-10 PRS Recommendation Report 061908 | doc | Jun 19 '08 | Committee Report |
| 107NPRR-11_TAC_Recommendation_Report_062608 | doc | Jun 27 '08 | Committee Report |
| 107NPRR-12 Board Action Report 071508 | doc | Jul 17 '08 | Committee Report |
Meetings That Took It Up 8
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '08 | ERCOT Board of Directors Meeting | BOARD | Concluded |
| Jun 26 '08 | TAC Meeting | TAC | Concluded |
| Jun 19 '08 | PRS Meeting | PRS | Concluded |
| May 28 '08 | Credit Work Group Meeting | CREDITWG | Concluded |
| May 22 '08 | PRS Meeting | PRS | Concluded |
| May 5 '08 | TPTF Meeting | TPTF | Concluded |
| Mar 20 '08 | PRS Meeting | PRS | Concluded |
| Mar 19 '08 | WMS Meeting | WMS | Concluded |