NPRR #1064 · Revision Request
NPRR1064 Identification of Chronic Congestion
- PRS May 13 '21
- TAC May 26 '21
- BOARD Jun 8 '21
- PUCT —
ReasonAdministrative
Created2021-02-11
Approved2021-06-08
Sections Affected
3.203.20.1and 3.20.2
Summary
The Nodal Protocol Revision Request (NPRR) better conforms Protocol language to ERCOT’s as-built systems with respect to the evaluation and reporting of chronic congestion. This NPRR also clarifies ERCOT’s expectations and processes regarding the verification of modeling information for elements that are included in the chronic congestion report.
Timeline
- Jan 26
-
Feb 11
PRS PRS Meeting by Webex OnlyPRSDeferred/Tabled Referred → ROS“to table NPRR1064 and refer the issue to ROS” — Passed→ Language Consideration
-
Mar 4
ROS ROS Meeting by Webex Only“To request PRS continue to table NPRR1064 to allow for review by NDSWG/OWG”
- Mar 11
-
Mar 18
Listed without action at 1 meeting
- Apr 1
-
Apr 15
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Amended by the Mar 24 '21 ERCOT comments“To recommend approval of NPRR1064 as amended by the 3/24/21 ERCOT comments” — Passed→ PRS for Impact Analysis consideration
-
May 13
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 4/15/21 PRS Report and Impact Analysis for NPRR1064” — Passed→ TAC for consideration
-
May 26
TAC TAC Meeting by Webex OnlyTACRecommended for Approval“To recommend approval of NPRR1064 as recommended by PRS in the 5/13/21 PRS Report” — Passed→ Board for consideration
- Jun 7
-
Jun 8
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve NPRR1064 as recommended by TAC in the 5/26/21 TAC Report” — Passed
-
—