NPRR #1049 · Revision Request
NPRR1049 Management of DC Tie Load Zone Modifications
- PRS Dec 10 '20
- TAC Jan 27 '21
- BOARD Feb 9 '21
- PUCT —
ReasonAddresses current operational issues
Created2020-11-11
Approved2021-02-09
Sections Affected
3.4.23.10.3.1
Summary
This Nodal Protocol Revision Request (NPRR) seeks to remove the requirement to obtain ERCOT Board approval to add, delete, or change a Direct Current Tie (DC Tie) Load Zone. This NPRR would also remove the 48-month waiting period before such actions can go into effect. Further, this NPRR would align the timeline for deleting DC Tie Load Zones with the timeline for removing Resource Nodes associated with a retiring Generation Resource.
Timeline
- Oct 22
-
Nov 11
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval“to recommend approval of NPRR1049 as submitted” — Passed→ Impact Analysis Consideration
-
Dec 10
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 11/11/20 PRS Report and the Impact Analysis for NPRR1049” — Passed→ Revision Request Consideration
-
Jan 27
TAC TAC Meeting by Webex OnlyTACRecommended for Approval“to recommend approval of NPRR1049 as recommended by PRS in the 12/10/20 PRS Report” — Passed→ Revision Request Consideration
-
Feb 9
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“to approve NPRR1049 as recommended by TAC in the 1/27/21 TAC Report” — Passed
-
—
Posted since the last meeting