NPRR #1037 · Revision Request
NPRR1037 Correction to the Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT
- PRS Sep 10 '20
- TAC Sep 23 '20
- BOARD Oct 13 '20
- PUCT —
ReasonAddresses current operational issues
Created2020-08-13
Approved2020-10-13
Sections Affected
6.6.12.1
Summary
This Nodal Protocol Revision Request (NPRR) provides a correction to the settlement of Switchable Generation Resources (SWGRs) when instructed by ERCOT to switch from a non-ERCOT Control Area to the ERCOT Control Area. Specifically, this NPRR includes “Operational Costs” (“OPCs”) incurred by the SWGR in the non-ERCOT Control Area in the calculation of the “Switchable Generation Operating Cost” (“SWOC”) for Resources with approved verifiable costs. OPC is currently included only for Resources without approved verifiable costs.
Timeline
- Jul 29
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1037 as submitted” — Passed→ Impact Analysis Consideration
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 8/13/20 PRS Report and Impact Analysis for NPRR1037” — Passed→ Revision Request Consideration
-
Sep 23
TAC TAC Meeting by Webex OnlyTACRecommended for Approval“to recommend approval of NPRR1037 as recommended by PRS in the 9/10/20 PRS Report” — Passed→ Revision Request Consideration
-
Oct 13
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“to approve NPRR1037 as recommended by TAC in the 9/23/20 TAC Report” — Passed
-
—
Posted since the last meeting