NPRR1037  Correction to the Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT

Approved sponsor ERCOT posted 2020-07-29 ercot.com
ReasonAddresses current operational issues
Created2020-08-13
Approved2020-10-13
Sections Affected
6.6.12.1
Summary
This Nodal Protocol Revision Request (NPRR) provides a correction to the settlement of Switchable Generation Resources (SWGRs) when instructed by ERCOT to switch from a non-ERCOT Control Area to the ERCOT Control Area. Specifically, this NPRR includes “Operational Costs” (“OPCs”) incurred by the SWGR in the non-ERCOT Control Area in the calculation of the “Switchable Generation Operating Cost” (“SWOC”) for Resources with approved verifiable costs. OPC is currently included only for Resources without approved verifiable costs.
Action Log 4 milestones
Ballots
DateBodyResultYesNoAbstain
Sep 23 '20 TAC Motion Passes 27 0 1 xls
Sep 10 '20 PRS Motion Carries 7 0 0 xls
Documents 9
NameTypePostedClassification
1037NPRR-01 Correction to the Settlement of Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT 072920 doc Jul 29 '20 Revision Request
1037NPRR-02 Impact Analysis 072920 docx Jul 29 '20 Staff Report
1037NPRR-03 PRS Ballot 081320 xls Aug 18 '20 Revision Request Ballot
1037NPRR-04 PRS Report 081320 doc Aug 18 '20 Committee Report
1037NPRR-05 PRS Ballot 091020 xls Sep 15 '20 Revision Request Ballot
1037NPRR-06 PRS Report 091020 doc Sep 15 '20 Committee Report
1037NPRR-07 TAC Ballot 092320 xls Sep 27 '20 Revision Request Ballot
1037NPRR-08 TAC Report 092320 doc Sep 27 '20 Committee Report
1037NPRR-09 Board Report 101320 doc Oct 16 '20 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Oct 13 '20 Urgent Board of Directors Meeting – Teleconference Available by Webcast BOARD Concluded
Sep 23 '20 TAC Meeting by Webex Only TAC Concluded
Sep 10 '20 PRS Meeting PRS Concluded
Aug 13 '20 PRS Meeting PRS Concluded