NPRR #1035 · Revision Request
NPRR1035 DC Tie Schedules Protected Information Expiry and Posting
- PRS Sep 10 '20
- TAC Sep 23 '20
- BOARD Oct 13 '20
- PUCT —
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2020-08-13
Approved2020-10-13
Sections Affected
1.3.1.11.3.1.41.3.3
Summary
This Nodal Protocol Revision Request (NPRR) requires ERCOT to publish all Direct Current Tie (DC Tie) Schedules 60 days after the Operating Day.
Timeline
- Jul 22
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1035 as submitted” — Passed→ Impact Analysis Consideration
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2021 · rank 3230“to endorse and forward to TAC the 8/13/20 PRS Report and Impact Analysis for NPRR1035 with a recommended effective date of upon ERCOT Board approval for Section 1.3.1.1 and upon system implementation for Section 1.3.3 with a recommended priority of 2021 and rank of 3230” — Passed→ Revision Request Consideration
-
Sep 23
TAC TAC Meeting by Webex OnlyTACRecommended for Approval Amended by the Sep 16 '20 ERCOT comments“to recommend approval of NPRR1035 as recommended by PRS in the 9/10/20 PRS Report as amended by the 9/16/20 ERCOT comments” — Passed→ Revision Request Consideration
-
Oct 13
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“to approve NPRR1035 as recommended by TAC in the 9/23/20 TAC Report” — Passed
-
—
Posted since the last meeting