NPRR #103 · Revision Request
NPRR103 Settlement of Power Imported via DC Ties and Block Load Transfer Under a Declared Emergency Condition
ReasonThe additions to the Settlement formulas included in this Nodal Protocol Revision Request (NPRR) are intended to make the QSE responsible for responding to the ERCOT Dispatch Instructions issued during a declared Emergency Condition an assured cost recovery. Charges to cover the payments described in this NPRR are included in Section 6.6.10, Real-Time Revenue Neutrality Allocation.
Created2008-02-21
Approved2008-04-15
Sections Affected
6.6.3.4Real-Time Energy for DC Tie Import 6.6.3.5Real-Time Payment for a Block Load Transfer Point
Summary
These revisions add Settlement formulas to pay a Qualified Scheduling Entity (QSE) for emergency energy imported over the DC Ties and for energy supplied to BLT Load moved from the ERCOT control area to a Non-ERCOT control area during a declared Emergency Condition. These payments may only be made for actions taken by the (QSE) in response to an ERCOT Dispatch Instruction.
Action Log 4 milestones
-
Apr 15
BOARDApproved
-
Feb 21
PRSRecommended for Approval→ PRS review of the Impact Analysis and Recommendation Report.
-
Mar 20
PRSRecommended for Approval→ TAC review of NPRR103.
-
Apr 4
TACRecommended for Approval→ ERCOT Board consideration of NPRR103.
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 21 '08 | PRS | To recommend approval of NPRR103 as revised by ERCOT comments and PRS. | Passed |
| Mar 20 '08 | PRS | To recommend approval of NPRR103 as revised by ERCOT Staff comments dated 3/19/08 and forward the IA and this Recommendation Report to TAC. | Passed |
Documents 9
| Name | Type | Posted | Classification |
|---|---|---|---|
| 103NPRR-01 Settlement of Power Imported via DC Ties and Block Lo | doc | Feb 13 '08 | Revision Request |
| 103NPRR-02 TPTF Voting Ballot 020408 | xls | Feb 4 '08 | Revision Request Ballot |
| 103NPRR-03 ERCOT Staff Comments 021908 | doc | Feb 19 '08 | Revision Request Comments |
| 103NPRR-04 PRS Recommendation Report 022108 | doc | Feb 26 '08 | Committee Report |
| 103NPRR-05 Impact Analysis Report 031308 | doc | Mar 13 '08 | Committee Report |
| 103NPRR-06 ERCOT Staff Comments 031908 | doc | Mar 19 '08 | Revision Request Comments |
| 103NPRR-07 PRS Recommendation Report 032008 | doc | Mar 25 '08 | Committee Report |
| 103NPRR-08 TAC Recommendation Report 040408 | doc | Apr 4 '08 | Committee Report |
| 103NPRR-09 Board Action Report 041508 | doc | Apr 16 '08 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 15 '08 | Board of Directors Meeting | BOARD | Concluded |
| Apr 4 '08 | TAC Meeting | TAC | Concluded |
| Mar 20 '08 | PRS Meeting | PRS | Concluded |
| Feb 21 '08 | PRS Meeting | PRS | Concluded |