NPRR098  Protocol Sections 4 and 6 Formula Clarifications and Related Revisions

Approved sponsor TPTF posted 2008-01-09 ercot.com
ReasonTo ensure that the formulas accurately reflect the desired calculations for certain Ancillary Services.
Created2008-01-17
Approved2008-03-18
Sections Affected
4.6.4.2Charges for Ancillary Services Procurement in the DAM; 6.6.7Voltage Support Settlement; 6.6.9.1Payment for Emergency Power increase directed by ERCOT; 6.7.3Real Time Settlements calculations for Ancillary Services
Summary
This Nodal Protocol Revision Request (NPRR) revises parts of Sections 4.6.4.2 and Sections 6.6.7, 6.6.9.1 and 6.7.3 to add clarity to the formulas for charges related to certain Ancillary Services and variable definitions or data elements.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Jan 17 '08PRS To recommend approval of NPRR098 as revised by ERCOT Staff comments.Passed
Documents 10
NameTypePostedClassification
096NPRR-05 PRS Recommendation Report 022108 doc Feb 25 '08 Committee Report
098NPRR-01 TPTF Voting Ballot 121807 xls Dec 20 '07 Revision Request Ballot
098NPRR-02 TPTF Voting Ballot 010808 xls Jan 8 '08 Revision Request Ballot
098NPRR-03 Protocol Sections 4 and 6 Formula Clarifications and doc Jan 9 '08 Revision Request
098NPRR-04 ERCOT Staff Comments 010908 doc Jan 9 '08 Revision Request Comments
098NPRR-06 ERCOT Impact Analysis 021408 doc Feb 14 '08 Staff Report
098NPRR-07 PRS Recommendation Report 011708 doc Feb 25 '08 Committee Report
098NPRR-08 PRS Recommendation Report 022108 doc Feb 25 '08 Committee Report
098NPRR-09 TAC Recommendation Report 030608 doc Mar 7 '08 Committee Report
098NPRR-10 Board Action Report 031808 doc Mar 18 '08 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Mar 18 '08 Board of Directors Meeting BOARD Concluded
Mar 6 '08 TAC Meeting TAC Concluded
Feb 21 '08 PRS Meeting PRS Concluded
Jan 17 '08 PRS Meeting PRS Concluded