NPRR #55 · Revision Request

NPRR055  Correction of Voltage Support QSE Total Bill Determinants

Approved sponsor Transition Plan Task Force (TPTF) posted 2007-03-27 ercot.com
ReasonDuring ERCOT Staff analysis of the settlement statement requirements it was discovered that "Voltage Support Service" and "Lost Opportunity Payments" were combined under one QSE Total. ERCOT Staff believes each charge type requires its own QSE Total in order for the settlement statement to reflect each charge type separately. ERCOT Staff created this NPRR for the purpose of transparency of the charge types.
Created2007-04-20
Approved2007-07-17
Sections Affected
6.6.79.5.3
Summary
This NPRR corrects Voltage Support QSE Total bill determinants and their calculations for the purpose of breaking out the Voltage Support Charge Types on the settlement statement.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
055NPRR-01 Correction of Voltage Support QSE Total Bill Determin doc Mar 27 '07 Revision Request
055NPRR-02 PRS Recommendation Report 042007 doc Apr 23 '07 Committee Report
055NPRR-03 B2 Impact Analysis 062107 doc Jun 22 '07 Staff Report
055NPRR-04 PRS Recommendation Report 062107 doc Jun 22 '07 Committee Report
055NPRR-05 TAC Recommendation Report 062807 doc Jul 2 '07 Committee Report
055NPRR-06 Board Action Report 071707 doc Jul 19 '07 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Jun 21 '07 PRS Meeting PRS Concluded
Jun 12 '07 PRS and TPTF: Joint Meeting PRS Concluded
Apr 20 '07 PRS Meeting PRS Concluded