NPRR #54 · Revision Request
NPRR054 Update of Nodal Protocols to Comply with NERC Name Change – Companion to PRR711
- PRS Jun 21 '07
- TAC May 4 '07
- BOARD May 16 '07
- PUCT —
ReasonUpdate of Nodal Protocols to accurately reflect NERC name change.
Created2007-03-22
Approved2007-05-16
Sections Affected
1.21.3.62.2and 6.5.9.1
Summary
This Nodal Protocol Revision Request (NPRR) updates Nodal Protocol References to reflect the recent NERC name change. NERC recently changed its name from North American Electric Reliability Council to North American Electric Reliability Corporation.
Timeline
- Mar 14
-
Mar 22
PRS PRS MeetingPRSRecommended for Approval“Recommend approval of NPRR054 as submitted.” — Passed→ Impact Analysis Review
-
Apr 20
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“Forward the Recommendation Report and IA to TAC for approval” — Passed
-
May 4
TAC TAC MeetingTACRecommended for Approval“Recommend approval of NPRR054 as recommended by PRS. All Market Segments were present for the vote.” — Passed
- May 16
- Jun 12
-
Jun 21
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“Endorse the revised IA and forward it to TAC.” — Passed
-
Jun 28
TACEmail Vote / Unlisted MeetingTAC“No Action.”