NPRR051  Removal of the Pseudo Resource Requirement in the Real Time Security Constrained Economic Dispatch (SCED) Process

Approved sponsor Trip Doggett on behalf of TPTF posted 2007-03-12 ercot.com
ReasonThe purpose of proceeding with this NPRR is to remove the pseudo resource concept from the ongoing ERCOT Business Requirements and Conceptual Design process to avoid waste of time and effort by the ERCOT Nodal Project Teams.
Created2007-03-22
Approved2007-07-17
Sections Affected
6.5.7.3
Summary
This NPRR removes the requirement to employ a pseudo resource from the SCED Process in Section 6.5.7.3.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Jun 12 '07PRS Endorse the B1G6 IA as revised by PRS and forward the document to TAC for approval.Passed
Documents 10
NameTypePostedClassification
051NPRR-01 Removal of Pseudo Resource 031207 doc Mar 12 '07 Revision Request
051NPRR-02 PRS Meeting Ballot 032207 xls Mar 22 '07 Revision Request Ballot
051NPRR-03 PRS Action Report 032207 doc Apr 10 '07 Committee Report
051NPRR-04 PRS Recommendation Report 042007 doc Apr 24 '07 Committee Report
051NPRR-05 Impact Analysis 060807 doc Jun 13 '07 Staff Report
051NPRR-06 B1G6 Impact Analysis 061207 doc Jun 13 '07 Staff Report
051NPRR-07 PRS Recommendation Report 061207 doc Jun 14 '07 Committee Report
051NPRR-08 TAC Recommendation Report 062807 doc Jul 2 '07 Committee Report
051NPRR-09 Board Action Report 071707 doc Jul 20 '07 Committee Report
Vote_NPRR_Removal_of_Pseudo_Resource_030707_carried corrected 01 xls Jan 2 '08 Revision Request Ballot
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Aug 13 '07 TPTF Meeting TPTF Concluded
Jun 12 '07 PRS and TPTF: Joint Meeting PRS Concluded
Apr 20 '07 PRS Meeting PRS Concluded
Mar 22 '07 PRS Meeting PRS Concluded