NPRR #51 · Revision Request
NPRR051 Removal of the Pseudo Resource Requirement in the Real Time Security Constrained Economic Dispatch (SCED) Process
- PRS Jun 12 '07
- TAC Jun 28 '07
- BOARD Jul 17 '07
- PUCT —
ReasonThe purpose of proceeding with this NPRR is to remove the pseudo resource concept from the ongoing ERCOT Business Requirements and Conceptual Design process to avoid waste of time and effort by the ERCOT Nodal Project Teams.
Created2007-03-22
Approved2007-07-17
Sections Affected
6.5.7.3
Summary
This NPRR removes the requirement to employ a pseudo resource from the SCED Process in Section 6.5.7.3.
Timeline
- Mar 12
- Mar 22
-
Apr 20
PRS PRS MeetingPRSRecommended for Approval“Recommend approval as submitted by TPTF” — Passed→ PRS consideration of the Impact Analysis
-
Jun 12
PRS PRS and TPTF: Joint MeetingPRSRecommended for Approval Forwarded → TAC“Endorse the B1G6 IA as revised by PRS and forward the document to TAC for approval.” — Passed→ Review of B1G6 Impact Analysis
-
Jun 28
TACEmail Vote / Unlisted MeetingTACRecommended for Approval“Recommend approval of NPRR051 and its IA as recommended by PRS.” — Passed
-
Jul 17
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve this NPRR as recommended by TAC.” — Passed
- Aug 13
-
—
Posted since the last meeting