NPRR #48 · Revision Request
NPRR048 Revised Wording of Opportunity Outages for Transmission Facilities
ReasonThis NPRR will give Transmission Operators enhanced ability to maintain, replace or upgrade transmission facilities that connect a Resource to the interconnected ERCOT system.
Created2007-03-22
Approved2007-07-17
Sections Affected
2.13.1.6.8
Summary
The proposed Opportunity Outages rewording will allow ERCOT to grant a TSP permission to work on TSP-owned equipment that can only be maintained when a Resource is off-line for a Forced, Planned or Maintenance Outage.
Action Log 4 milestones
-
Mar 22
PRSRecommended for Approval→ PRS consideration of the Impact Analysis
-
Jun 12
PRSRecommended for Approval→ Review of B1G1 Impact Analysis
-
Jun 28
TACRecommended for Approval→ Board consideration of this NPRR and its IA
-
Jul 17
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Mar 22 '07 | PRS | Recommend for approval as revised by ERCOT Staff comments | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 048NPRR-01 Revised Wording of Opportunity Outages for Transmissi | doc | Mar 8 '07 | Revision Request |
| 048NPRR-02 ERCOT Comments 031407 | doc | Mar 14 '07 | Revision Request Comments |
| 048NPRR-03 PRS Recommendation Report 032207 | doc | Mar 23 '07 | Committee Report |
| 048NPRR-04 B1G1 Impact Analysis 060507 | doc | Jun 15 '07 | Staff Report |
| 048NPRR-05 PRS Recommendation Report 061207 | doc | Jun 14 '07 | Committee Report |
| 048NPRR-06 TAC Recommendation Report 062807 | doc | Jul 2 '07 | Committee Report |
| 048NPRR-07 Board Action Report 071707 | doc | Jul 20 '07 | Committee Report |
| Vote_Opportunity_Outage_NPRR_03107_carried corrected 010208 | xls | Jan 2 '08 | Revision Request Ballot |
Meetings That Took It Up 2
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 12 '07 | PRS and TPTF: Joint Meeting | PRS | Concluded |
| Mar 22 '07 | PRS Meeting | PRS | Concluded |