NPRR #29 · Revision Request
NPRR029 Network Model Testing Clarification
ReasonTo clarify testing processes and requirements.
Created2006-09-21
Approved2006-10-17
Sections Affected
3.10.13.10.4
Summary
Divides the model testing into real time testing, and simulation testing.
Action Log 5 milestones
-
Sep 21
PRSRecommended for Approval→ TAC consideration
-
Oct 6
TACRecommended for Approval→ Board consideration
-
Oct 17
BOARDApproved→ Effective Upon Texas Nodal Market Implementation
-
Jun 12
PRSRecommended for Approval→ Review of B1G11 Impact Analysis
-
Jun 28
TACRecommended for Approval→ Board of Directors consideration of this NPRR and its IA
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 029NPRR-01 Network Model Testing Clarification 091506 | doc | Sep 15 '06 | Revision Request |
| 029NPRR-02 Impact Analysis 091506 | doc | Sep 15 '06 | Staff Report |
| 029NPRR-03 PRS Recommendation Report 092106 | doc | Sep 26 '06 | Committee Report |
| 029NPRR-04 TAC Recommendation Report 100606 | doc | Oct 6 '06 | Committee Report |
| 029NPRR-05 BOD Action Report 101706 | doc | Oct 19 '06 | Committee Report |
| 029NPRR-06 Impact Analysis 060807 | doc | Jun 8 '07 | Staff Report |
| 029NPRR-07 B1G11 Impact Analysis 061207 | doc | Jun 13 '07 | Staff Report |
| 029NPRR-08 PRS Recommendation Report 061207 | doc | Jun 15 '07 | Committee Report |
| 029NPRR-09 TAC Recommendation Report 062807 | doc | Jul 2 '07 | Committee Report |
| 029NPRR-10 Board Action Report 071707 | doc | Jul 20 '07 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 12 '07 | PRS and TPTF: Joint Meeting | PRS | Concluded |
| Oct 17 '06 | ERCOT Board of Directors Meeting | BOARD | Concluded |
| Oct 6 '06 | TAC Meeting | TAC | Concluded |
| Sep 21 '06 | PRS Meeting | PRS | Concluded |