ERCOT·WATCH Search ercot.com  ⌕
NPRR #2 · Revision Request

NPRR002  Section 3, Zonal PRR Synchronization and ERCOT Staff Clarifications

Approved sponsor TPTF posted 2006-05-19 ercot.com
ReasonTo incorporate into the Draft Nodal Protocols provisions approved by the Board for the Zonal market and determined by the ERCOT stakeholders to be relevant to the Nodal market.
Created2006-06-22
Approved2007-07-17
Sections Affected
3
Summary
This NPRR incorporates relevant language from the following PRRs that were approved by the Board between April 2004 and February 2006: PRR492, Plan to Alleviate Chronic Local Congestion; PRR513, Verification of Operational Model after Recurring Local Congestion Event; PRR576, Disclosure of OOME, OOMC, and RMR Service; PRR596, Mothballed Generation Resource Estimated Return to Service Dates/PRR573, Mothballed Generation Resource Definition and Time to Service Updates; PRR581, Update RMR Language Due to PUC Rule 25.502; PRR627, RMR Transmission Issues and RMR Contract Extension; and PRR633, TSP Data Information Requirements. PRR307, Controllable Resources, was part of the TNT synchronization because a portion of the PRR language in the current zonal protocols was inadvertently not included in the nodal protocols section 3.17.2(2). This NPRR also incorporates TPTF determinations regarding ERCOT Staff clarification questions as documented in the ERCOT Clarification Matrix for Section 3 and discussed by TPTF and 3/29/06, 4/10/06 and 4/11/06.
Action Log 8 milestones
Amendments
DateBodyMotionResult
Jun 12 '07PRS Endorse the B1G6 IA as revised by PRS and forward the document to TAC for approval.Passed
Documents 15
NameTypePostedClassification
002NPRR-01 Section 3 PRR Synchronization and ERCOT Staff Clarifi doc May 17 '06 Revision Request
002NPRR-02 ERCOT Staff Comments 061406 doc Jun 14 '06 Revision Request Comments
002NPRR-03 NDSWG Comments 062006 doc Jun 20 '06 Revision Request Comments
002NPRR-04 PRS Action Report 062206 doc Jul 11 '06 Committee Report
002NPRR-05 TPTF Comments 071306 doc Jul 13 '06 Revision Request Comments
002NPRR-06 Impact Analysis 071306 doc Jul 13 '06 Staff Report
002NPRR-07 PRS Recommendation Report 072006 doc Jul 25 '06 Committee Report
002NPRR-08 TAC Recommendation Report 080306 doc Aug 4 '06 Committee Report
002NPRR-09 BOD Action Report 081506 doc Aug 21 '06 Committee Report
002NPRR-10 Impact Analysis 060807 doc Jun 13 '07 Staff Report
002NPRR-11 B1G6 Impact Analysis 061207 doc Jun 13 '07 Staff Report
002NPRR-12 PRS Recommendation Report 061207 doc Jun 14 '07 Committee Report
002NPRR-13 TAC Recommendation Report 062807 doc Jul 2 '07 Committee Report
002NPRR-14 Board Action Report 071707 doc Jul 20 '07 Committee Report
BallotVote-NPRR3 041006 TPTF corrected 010208 xls Jan 2 '08 Revision Request Ballot
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Jun 12 '07 PRS and TPTF: Joint Meeting PRS Concluded
Aug 15 '06 ERCOT Board of Directors Meeting BOARD Concluded
Aug 3 '06 TAC Meeting TAC Concluded
Jul 20 '06 PRS Meeting PRS Concluded
Jul 10 '06 TPTF Meeting TPTF Concluded
Jun 22 '06 PRS Meeting PRS Concluded