NOGRR #258 · Revision Request

NOGRR258  Related to NPRR1198, Congestion Mitigation Using Topology Reconfigurations

Approved sponsor EDF Renewables, Inc. posted 2023-08-31 ercot.com
ReasonStrategic Plan Objective 2
Created2023-10-05
Approved2024-07-25
Sections Affected
11.111.411.4.111.611.8 (new)and 11.8.1 (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) proposes changes to align the Nodal Operation Guides with NPRR1198 that adds language to allow the use of Remedial Action Plans (RAPs) and Extended Action Plans (EAPs) to facilitate the market use of the ERCOT Transmission Grid. NOGRR258 also adds guardrails to ensure that topology reconfiguration requests meet basic reliability and economic criteria, and defines the process for submission, review, and approval of EAPs. This NOGRR and NPRR1198 leverage ERCOT’s existing Constraint Management Plan (CMP) process to quickly mitigate critical transmission congestion impacts by establishing a scalable process for topology reconfiguration requests that is transparent, predictable, equitable, workable, reliable, and compatible with existing planning processes. ERCOT already leverages topology optimization in the CMP processes. Since NPRR529, Congestion Management Plan was introduced in 2013 with the limitations that NPRR1198 proposes to revise, the power industry has evolved and there have been technological improvements that make transmission topology reconfigurations a powerful option to mitigate congestion beyond just use cases for which there is no feasible Security-Constrained Economic Dispatch (SCED) solution.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Apr 4 '24ROS to recommend approval of NOGRR258 as amended by the 3/8/24 LCRA comments as revised by ROSPassed
Ballots
DateBodyResultYesNoAbstain
May 22 '24 TAC Motion Passes 25 0 4 xls
May 2 '24 ROS Motion Carries 7.5 0 3 xls
Apr 4 '24 ROS Motion Carries 7.5 0 4 xls
Oct 5 '23 ROS Motion Carries 7.5 0 0 xls
Documents 22
NameTypePostedClassification
258NOGRR-01 Related to NPRR1198, Congestion Mitigation Using Topology Reconfigurations docx Aug 31 '23 Revision Request
258NOGRR-02 ROS Ballot 100523 xls Oct 10 '23 Revision Request Ballot
258NOGRR-03 ROS Report 100523 docx Oct 10 '23 Committee Report
258NOGRR-04 DC Energy Comments 102323 docx Oct 23 '23 Revision Request Comments
258NOGRR-05 EDF Renewables Comments 103023 docx Oct 30 '23 Revision Request Comments
258NOGRR-06 STEC Comments 111423 docx Nov 14 '23 Revision Request Comments
258NOGRR-07 Oncor Comments 012224 docx Jan 22 '24 Revision Request Comments
258NOGRR-08 EDF Renewables Comments 021624 docx Feb 16 '24 Revision Request Comments
258NOGRR-09 LCRA Comments 021624 docx Feb 16 '24 Revision Request Comments
258NOGRR-10 LCRA Comments 030824 docx Mar 8 '24 Revision Request Comments
258NOGRR-11 Sandy Creek Associates Comments 031224 docx Mar 12 '24 Revision Request Comments
258NOGRR-12 AWEP Comments 032824 docx Mar 28 '24 Revision Request Comments
258NOGRR-13 EDF Renewables Comments 040124 doc Apr 1 '24 Revision Request Comments
258NOGRR-14 ROS Ballot 040424 xls Apr 9 '24 Revision Request Ballot
258NOGRR-15 ROS Report 040424 docx Apr 9 '24 Committee Report
258NOGRR-16 Impact Analysis 043024 docx Apr 30 '24 Staff Report
258NOGRR-17 ROS Ballot 050224 xls May 6 '24 Revision Request Ballot
258NPGRR-18 ROS Report 050224 docx May 6 '24 Committee Report
258NOGRR-19 TAC Ballot 052224 xls May 23 '24 Revision Request Ballot
258NOGRR-20 TAC Report 052224 docx May 23 '24 Committee Report
258NOGRR-21 Board Report 061824 docx Jun 20 '24 Committee Report
258NOGRR-22 PUCT Report 072525 docx Jul 29 '24 Committee Report
Meetings That Took It Up 19
DateMeetingCommitteeStatus
Jun 18 '24 Board of Directors Meeting BOARD Concluded
May 22 '24 TAC Meeting TAC Concluded
May 2 '24 ROS Meeting - Webex Only ROS Concluded
Apr 4 '24 ROS Meeting ROS Concluded
Mar 13 '24 OWG Meeting - Webex Only OWG Concluded
Mar 7 '24 ROS Meeting - Webex Only ROS Concluded
Feb 20 '24 OWG Meeting - Webex Only OWG Concluded
Feb 1 '24 ROS Meeting - Webex Only ROS Concluded
Jan 23 '24 OWG Meeting - Webex Only OWG Concluded
Jan 8 '24 ROS Meeting ROS Concluded
Dec 7 '23 ROS Meeting - Webex Only ROS Concluded
Dec 5 '23 NDSWG NPRR1198 Discussion - Webex Only NDSWG Concluded
Nov 16 '23 OWG Meeting - Webex Only OWG Concluded
Nov 2 '23 ROS Meeting ROS Concluded
Oct 19 '23 OWG Meeting - Webex Only OWG Concluded
Oct 11 '23 WMS Meeting WMS Concluded
Oct 5 '23 ROS Meeting - Webex Only ROS Concluded
Sep 21 '23 OWG Meeting - Webex Only OWG Concluded
Sep 7 '23 ROS Meeting ROS Concluded