NOGRR #250 · Revision Request
NOGRR250 Related to NPRR 1171, Requirements for DGRs and DESRs on Circuits Subject to Load Shedding
- ROS Aug 3 '23
- TAC Aug 22 '23
- BOARD Aug 31 '23
- PUCT Oct 12 '23
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2023-05-04
Approved2023-10-12
Sections Affected
2.6.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) removes language that prohibits Distribution Service Providers (DSPs) from connecting Distribution Generation Resources (DGRs) and Distribution Energy Storage Resources (DESRs) to circuits included in an Under-Frequency Load Shed (UFLS) scheme to align with NPRR1171. NPRR1171 recognizes that some DGRs and DESRs may be connected to circuits that are subject to Load shed.
Timeline
- Mar 29
-
May 4
ROS ROS Meeting - Webex OnlyROSDeferred/Tabled Referred → OWG“to table NOGRR250 and refer the issue to the Operations Working Group (OWG)” — Passed→ Language Consideration
- May 18
-
Jun 8
Listed without action at 2 meetings (Jun 8 '23 – Jun 22 '23)
-
Jul 6
ROS ROS Meeting - Webex OnlyROSRecommended for Approval“to recommend approval of NOGRR250 as submitted” — Passed→ Impact Analysis Consideration
-
Aug 3
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 7/6/23 ROS Report and 3/29/23 Impact Analysis for NOGRR250” — Passed→ Revision Request Consideration
-
Aug 22
TAC TAC Meeting - Webex OnlyTACRecommended for Approval“to recommend approval of NOGRR250 as recommended by ROS in the 8/3/23 ROS Report” — Passed→ Revision Request Consideration
-
Aug 31
BOARD Board of Directors MeetingBOARDRecommended for Approval“to recommend approval of NOGRR250 as recommended by TAC in the 8/22/23 TAC Report” — Passed→ Revision Request Consideration
-
Oct 12
PUCTPUCTApproved“to approve NOGRR250 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting