ERCOT·WATCH Search ercot.com  ⌕
NOGRR #235 · Revision Request

NOGRR235  Combining Greyboxes and Other Corrections

Approved sponsor ERCOT posted 2021-10-20 ercot.com
ReasonAdministrative
Created2021-11-04
Approved2022-02-10
Sections Affected
2.9.13.3.2.1and 6.1.3.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) is submitted for transparency purposes to make small corrections to blackline and greybox language associated with NOGRR210, Related to NPRR1005, Clarify Definition of Point of Interconnection (POI) and Add Definition Point of Interconnection Bus (POIB), and NOGRR227, Add Phasor Measurement Recording Equipment Location for Main Power Transformer for Intermittent Renewable Resource (IRR), and to combine greyboxes at Section 3.3.2.1.
Action Log 4 milestones
Ballots
DateBodyResultYesNoAbstain
Jan 31 '22 TAC Motion Passes 30 0 0 xls
Dec 2 '21 ROS Motion Carries 7.5 0 0 xls
Nov 4 '21 ROS Motion Carries 7.5 0 0 xls
Documents 9
NameTypePostedClassification
235NOGRR-01 Combining Greyboxes and Other Corrections 102021 doc Oct 20 '21 Revision Request
235NOGRR-02 Impact Analysis 102021 doc Oct 20 '21 Staff Report
235NOGRR-03 ROS Ballot 110421 xls Nov 9 '21 Revision Request Ballot
235NOGRR-04 ROS Report 110421 doc Nov 9 '21 Committee Report
235NOGRR-05 ROS Ballot 120221 xls Dec 7 '21 Revision Request Ballot
235NOGRR-06 ROS Report 120221 doc Dec 7 '21 Committee Report
235NOGRR-07 TAC Ballot 013122 xls Feb 3 '22 Revision Request Ballot
235NOGRR-08 TAC Report 013122 doc Feb 3 '22 Committee Report
235NOGRR-09 PUCT Report 021022 doc Feb 15 '22 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Jan 31 '22 TAC Meeting by Webex Only TAC Concluded
Dec 2 '21 ROS Meeting by Webex Only ROS Concluded
Nov 4 '21 ROS Meeting by Webex Only ROS Concluded