NOGRR #208 · Revision Request
NOGRR208 Related to NPRR1002, BESTF-5 Energy Storage Resource Single Model Registration and Charging Restrictions in Emergency Conditions
- ROS Jul 9 '20
- TAC Jul 29 '20
- BOARD Aug 11 '20
- PUCT —
ReasonAddresses current operational issues. Market efficiencies or enhancements.
Created2020-06-04
Approved2020-08-11
Sections Affected
3.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guide with the Nodal Protocols as modified by NPRR1002, except Section 4.5.3.3, EEA Levels, which an Alignment NOGRR will be filed following approval of NPRR1002 to align with the Protocols.
Timeline
- Feb 25
-
May 7
Listed without action at 2 meetings (May 7 '20 – May 21 '20)
-
Jun 4
ROS ROS MeetingROSRecommended for Approval“To recommend approval of NOGRR208 as submitted” — Passed→ ROS for Impact Analysis consideration
-
Jul 9
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 6/4/20 ROS Report and Impact Analysis for NOGRR208” — Passed→ TAC for consideration
-
Jul 29
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NOGRR208 as recommended by ROS in the 7/9/20 ROS Report” — Passed→ Board for consideration
-
Aug 11
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“To approve NOGRR208 as recommended by TAC in the 7/29/20 TAC Report” — Passed
-
—
Posted since the last meeting