NOGRR #195 · Revision Request
NOGRR195 Generator Voltage Control Tolerance Band
- ROS Jul 9 '20
- TAC Jul 29 '20
- BOARD Aug 11 '20
- PUCT —
ReasonAddresses current operational issues
Created2019-09-05
Approved2020-08-11
Sections Affected
2.2.102.7.3.12.7.3.32.7.3.42.7.3.5
Summary
This Nodal Operating Guide Revision Request (NOGRR) addresses ERCOT audit recommendations from Texas Reliability Entity, Inc. (Texas RE) and proposes to modify generator voltage control tolerance bands.
Timeline
- Aug 20
-
Sep 5
ROS ROS MeetingROSDeferred/Tabled“to table NOGRR195 for one month” — Passed→ Language Consideration
-
Oct 3
ROS ROS MeetingROSDeferred/Tabled Referred → VPWG Referred → OWG“to table NOGRR195 and refer the issue to the Voltage Profile Working Group (VPWG) and Operations Working Group (OWG)” — Passed→ Language Consideration
- Oct 17
-
Nov 7
Listed without action at 8 meetings (Nov 7 '19 – Feb 20 '20)
- Mar 5
-
Mar 19
Listed without action at 2 meetings (Mar 19 '20 – May 7 '20)
-
Jun 4
ROS ROS MeetingROSRecommended for Approval Amended by the Jun 2 '20 LCRA comments“to recommend approval of NOGRR195 as amended by the 6/2/20 LCRA comments” — Passed→ Impact Analysis Consideration
-
Jul 9
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC Amended by the Jul 8 '20 ERCOT comments priority 2020 · rank 300“to endorse and forward to TAC the 6/4/20 ROS Report as amended by the 7/8/20 ERCOT comments and the Impact Analysis for NOGRR195 with a priority of 2020 and rank of 300” — Passed→ Revision Request Consideration
- Jul 16
-
Jul 29
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NOGRR195 as recommended by ROS in the 7/9/20 ROS Report” — Passed→ Revision Request Consideration
-
Aug 11
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“to approve NOGRR195 as recommended by TAC in the 7/29/20 TAC Report” — Passed
-
—
Posted since the last meeting