NOGRR #187 · Revision Request

NOGRR187  Related to NPRR863, Creation of ERCOT Contingency Reserve Service and Revisions to Responsive Reserve

Approved sponsor STEC posted 2019-03-06 ercot.com
ReasonMarket efficiencies or enhancements
Created2019-04-04
Approved2019-08-13
Sections Affected
1.42.2.42.2.4.12.2.4.22.32.3.1.22.3.1.2.1 (new)2.3.3 (new)2.3.3.1 (new)3.44.5.24.84.8.18F8Gand 9.4.6 (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guide with revisions to Ancillary Services proposed by NPRR863.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Jul 24 '19TAC To recommend approval of NOGRR187 as recommended by ROS in the 7/11/19 ROS Report as revised by TACPassed
Documents 7
NameTypePostedClassification
187NOGRR-01 Related to NPRR863, Creation of ERCOT Contingency Reserve Service and Revisions to Responsive Reserve 030619 docx Mar 6 '19 Revision Request
187NOGRR-02 ROS Report 040419 docx Apr 5 '19 Committee Report
187NOGRR-03 ROS Report 050219 docx May 6 '19 Committee Report
187NOGRR-04 Impact Analysis 061819 docx Jun 18 '19 Staff Report
187NOGRR-05 ROS Report 071119 docx Jul 12 '19 Committee Report
187NOGRR-06 TAC Report 072419 docx Jul 26 '19 Committee Report
187NOGRR-07 Board Report 081319 docx Aug 15 '19 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Aug 13 '19 Board of Directors Meeting BOARD Concluded
Jul 24 '19 TAC Meeting TAC Concluded
Jul 11 '19 ROS Meeting ROS Concluded
May 2 '19 ROS Meeting ROS Concluded
Apr 4 '19 ROS Meeting ROS Concluded