NOGRR #182 · Revision Request
NOGRR182 Transmission Operator (TO) Emergency Operations Plan Submittals
ReasonRegulatory requirements
Created2018-10-11
Sections Affected
3.7
Summary
This Nodal Operating Guide Revision Request (NOGRR) harmonizes the Transmission Operator (TO) emergency operations plan submittals with the North American Electric Reliability Corporation (NERC) Reliability Standard EOP-011-1, Emergency Operations. Currently there is a timing issue with TO emergency operations plans being submitted days and weeks leading up to ERCOT’s annual review, which begins on February 15. Since ERCOT has to review each TO’s plan within 30 days of receipt, ERCOT is clarifying that receipt is deemed to be on February 15 for the annual effort to review the plans collectively within the 30 days.
Action Log 3 milestones
-
Oct 11
ROSRecommended for Approval→ Impact Analysis Consideration
-
Nov 8
ROSRecommended for Approval→ Revision Request Consideration
-
Nov 29
TACApproved
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 182NOGRR-01 Transmission Operator (TO) Emergency Operations Plan Submittals 091018 | doc | Sep 10 '18 | Revision Request |
| 182NOGRR-02 Impact Analysis 091018 | doc | Sep 10 '18 | Staff Report |
| 182NOGRR-03 ROS Report 101118 | doc | Oct 16 '18 | Committee Report |
| 182NOGRR-04 ROS Report 110818 | doc | Nov 12 '18 | Committee Report |
| 182NOGRR-05 TAC Report 112918 | doc | Nov 29 '18 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 29 '18 | TAC Meeting | TAC | Concluded |
| Nov 8 '18 | ROS Meeting | ROS | Concluded |
| Oct 11 '18 | ROS Meeting | ROS | Concluded |
| Sep 20 '18 | OWG Meeting | OWG | Concluded |