ERCOT·WATCH Search ercot.com  ⌕
NOGRR #182 · Revision Request

NOGRR182  Transmission Operator (TO) Emergency Operations Plan Submittals

Approved sponsor ERCOT posted 2018-09-10 ercot.com
ReasonRegulatory requirements
Created2018-10-11
Sections Affected
3.7
Summary
This Nodal Operating Guide Revision Request (NOGRR) harmonizes the Transmission Operator (TO) emergency operations plan submittals with the North American Electric Reliability Corporation (NERC) Reliability Standard EOP-011-1, Emergency Operations. Currently there is a timing issue with TO emergency operations plans being submitted days and weeks leading up to ERCOT’s annual review, which begins on February 15. Since ERCOT has to review each TO’s plan within 30 days of receipt, ERCOT is clarifying that receipt is deemed to be on February 15 for the annual effort to review the plans collectively within the 30 days.
Action Log 3 milestones
Documents 5
NameTypePostedClassification
182NOGRR-01 Transmission Operator (TO) Emergency Operations Plan Submittals 091018 doc Sep 10 '18 Revision Request
182NOGRR-02 Impact Analysis 091018 doc Sep 10 '18 Staff Report
182NOGRR-03 ROS Report 101118 doc Oct 16 '18 Committee Report
182NOGRR-04 ROS Report 110818 doc Nov 12 '18 Committee Report
182NOGRR-05 TAC Report 112918 doc Nov 29 '18 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Nov 29 '18 TAC Meeting TAC Concluded
Nov 8 '18 ROS Meeting ROS Concluded
Oct 11 '18 ROS Meeting ROS Concluded
Sep 20 '18 OWG Meeting OWG Concluded