NOGRR #155 · Revision Request
NOGRR155 Voltage Ride-Through Requirements Clarification
- ROS Jul 7 '16
- TAC Jul 28 '16
- BOARD —
- PUCT —
ReasonAddresses current operational issues
Created2016-03-24
Sections Affected
2.9
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies Voltage Ride-Through (VRT) performance requirements for all Generation Resources immediately following a fault. This NOGRR stipulates that, in addition to remaining On-Line and connected to the transmission system following a fault, Generation Resources must also maintain real power.
Timeline
- Mar 9
-
Mar 24
OWG OWG MeetingOWGDeferred/Tabled“To table NOGRR150 for one month.” — Passed→ Language Consideration
-
Apr 22
OWG OWG MeetingOWGDeferred/Tabled“To table NOGRR155 for one month.” — Passed→ Language Consideration
-
May 19
OWG OWG MeetingOWGRecommended for Approval Amended by the May 16 '16 ERCOT comments“To recommend approval of NOGRR155 as amended by the 5/16/16 ERCOT comments.” — Passed→ Impact Analysis Consideration
-
Jun 23
OWG OWG MeetingOWGRecommended for Approval Forwarded → ROS“To endorse and forward to ROS the 5/19/16 OWG Report and the Impact Analysis for NOGRR155.” — Passed→ Revision Request Consideration
-
Jul 7
ROS ROS MeetingROSRecommended for Approval“To recommend approval of NOGRR155 as recommended by OWG in the 6/23/16 OWG Report.” — Passed→ Revision Request Consideration
-
Jul 28
TAC TAC MeetingTACApproved“To approve NOGRR155 as recommended by ROS in the 7/7/16 ROS Report.” — Passed
-
—
Posted since the last meeting