NOGRR #152 · Revision Request

NOGRR152  Restore Synchrony Between Contingency Planning for Minimum Level of Responsive Reserve Service and Real Time Contingency Analysis

Rejected sponsor Apex CAES, LLC, Calpine Corporation, First Solar Inc., GDF Suez Energy Marketing North America Inc., Golden Spread Electric Cooperative, Lower Colorado River Authority, Luminant Energy Company LLC, South Texas Electric Cooperative, SunEdison Inc., SunPower Corporation, and Talen Energy posted 2016-01-06 ercot.com
ReasonAddresses current operational issues and restores alignment between the contingency planning for the minimum level of RRS and the transmission security analysis in RTCA that has been inadvertently lost as capacity upgrades were made to STP that are not captured in the RRS analysis. This alignment has become more important as the percentage of generation on the system that does not contribute with governor-like Primary Frequency Response can be in excess of 10,000 MW even during Summer peak conditons.
Created2016-01-26
Rejected2016-04-07
Sections Affected
2.3.1.1
Summary
Align consideration of the simultaneous loss of the South Texas Nuclear Project (STP) as a credible single contingency for purposes of determining the minimum amount of Responsive Reserve (RRS) as it is currently used in the Real-Time Contingency Analysis (RTCA).
Action Log 4 milestones
Ballots
DateBodyResultYesNoAbstain
Apr 7 '16 ROS Motion Carries 5.5 2 2 xls
Documents 8
NameTypePostedClassification
152NOGRR-01 Restore Synchrony Between Contingency Planning for Minimum Level of Responsive Reserve Service and Real Time Contingency Analysis 010616 doc Jan 6 '16 Revision Request
152NOGRR-02 OWG Report 012616 doc Jan 29 '16 Committee Report
152NOGRR-03 ERCOT Comments 021716 doc Feb 17 '16 Revision Request Comments
152NOGRR-04 OWG Report 021816 doc Feb 19 '16 Committee Report
152NOGRR-05 ERCOT Comments 032316 doc Mar 23 '16 Revision Request Comments
152NOGRR-06 OWG Report 032416 doc Mar 28 '16 Committee Report
152NOGRR-07 ROS Report 040716 doc Apr 8 '16 Committee Report
152NOGRR-08 ROS Voting Ballot 040716 xls Apr 8 '16 Revision Request Ballot
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Apr 7 '16 ROS Meeting ROS Concluded
Mar 24 '16 OWG Meeting OWG Concluded
Feb 18 '16 OWG Meeting OWG Concluded
Jan 26 '16 OWG Meeting OWG Concluded