Approved sponsor Tenaska Power Services Co. posted 2012-07-26 ercot.com
ReasonOutages of interconnection points between the ERCOT and non-ERCOT Control Areas have market implications on both the ERCOT market and the interconnected market. Detailed information regarding such outages is necessary for Market Participants on both sides of the interconnection point to be able to manage risk associated with such outages.
Created2012-08-15
Approved2013-03-19
Sections Affected
10 (new)10.1 (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) provides that ERCOT shall produce a detailed report regarding any outage of a Direct Current Tie (DC Tie) in a timely manner.
Action Log 8 milestones
Amendments
DateBodyMotionResult
Aug 15 '12OWG Consensus to recommend approval of NOGRR101 as revised by the 8/13/12 ERCOT comments
Oct 17 '12OWG Consensus to recommend approval of NOGRR101 as amended by the 10/17/12 ERCOT comments
Dec 6 '12ROS To recommend approval of NOGRR101 as amended by the 10/22/12 Tenaska Power Services Co. comments and as revised by ROS with a recommended priority of 2013 and rank of 815Passed
Jan 17 '13PRS To endorse and forward the 12/6/12 ROS Report as amended by the 1/14/13 ERCOT comments and as revised by PRS and the Impact analysis for NOGRR101 to TAC with a recommended priority of 2013 and rank of 815Passed
Documents 18
NameTypePostedClassification
101NOGRR-01 Market Transparency for DC Tie Outage Information 07 doc Jul 26 '12 Revision Request
101NOGRR-02 Calpine Comments 073012 doc Jul 30 '12 Revision Request Comments
101NOGRR-03 ERCOT Comments 081312 doc Aug 15 '12 Revision Request Comments
101NOGRR-04 OWG Report 081512 doc Aug 16 '12 Committee Report
101NOGRR-05 WMS Comments 081612 doc Aug 16 '12 Revision Request Comments
101NOGRR-08 ERCOT Comments 101712 doc Oct 17 '12 Revision Request Comments
101NOGRR-09 OWG Report 101712 doc Oct 21 '12 Committee Report
101NOGRR-10 Tenaska Power Services Co. Comments 102212 doc Oct 22 '12 Revision Request Comments
101NOGRR-11 Impact Analysis 110712 doc Nov 7 '12 Staff Report
101NOGRR-12 OWG Report 111412 doc Nov 16 '12 Committee Report
101NOGRR-13 ERCOT Comments 112012 doc Nov 20 '12 Revision Request Comments
101NOGRR-14 ROS Report 120612 doc Dec 6 '12 Committee Report
101NOGRR-15 ERCOT Comments 121212 doc Dec 12 '12 Revision Request Comments
101NOGRR-16 PRS Report 121312 doc Dec 18 '12 Committee Report
101NOGRR-17 ERCOT Comments 011413 doc Jan 14 '13 Revision Request Comments
101NOGRR-18 PRS Report 011713 doc Jan 21 '13 Committee Report
101NOGRR-19 TAC Report 020713 doc Feb 8 '13 Committee Report
101NOGRR-20 Board Report 031913 doc Mar 22 '13 Committee Report
Meetings That Took It Up 12
DateMeetingCommitteeStatus
Mar 19 '13 Board of Directors Meeting BOARD Concluded
Feb 7 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Jan 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 13 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 6 '12 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Nov 14 '12 Operations Working Group (OWG) Meeting OWG Concluded
Oct 17 '12 Operations Working Group (OWG) Meeting OWG Concluded
Oct 16 '12 Market Information System User Group (MISUG) Meeting MIS Concluded
Aug 15 '12 Operations Working Group (OWG) Meeting OWG Concluded
Aug 15 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Aug 14 '12 Market Information System User Group (MISUG) Meeting MIS Concluded
Aug 9 '12 Joint QMWG and ETWG Meeting QMWG Concluded