NOGRR #98 · Revision Request
NOGRR098 Change of Facility Submission Time Lines to Align with Protocols
ReasonTo align and clarify the Nodal Operating Guides with paragraph (10) of Protocol Section 3.10, Network Operations Modeling and Telemetry, and paragraph (3) of Protocol Section 3.10.1, Time Line for Network Operations Model Changes, which outlines the time line for Transmission Service Provider (TSP) and Resource Entity submissions of Network Operations Model updates.
Created2012-06-13
Sections Affected
5.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies the submission time line for facility reactive capability and other modeling information.
Action Log 4 milestones
-
Jun 13
OWGRecommended for Approval→ OWG IA Review
-
Jul 18
OWGRecommended for Approval→ ROS Consideration
-
Aug 16
ROSRecommended for Approval→ TAC Consideration
-
Sep 7
TACApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 098NOGRR-01 Change of Facility Submission Time Lines to Align wi | doc | May 25 '12 | Revision Request |
| 098NOGRR-02 Impact Analysis 052512 | doc | May 25 '12 | Staff Report |
| 098NOGRR-03 OWG Report 061312 | doc | Jun 18 '12 | Committee Report |
| 098NOGRR-04 OWG Report 071812 | doc | Jul 19 '12 | Committee Report |
| 098NOGRR-05 ROS Report 081612 | doc | Aug 16 '12 | Committee Report |
| 098NOGRR-06 TAC Report 090712 | doc | Sep 10 '12 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Sep 7 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Aug 16 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Jul 18 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Jun 13 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |