NOGRR #97 · Revision Request
NOGRR097 New Section 8I, Black Start Resource Availability Test Form
ReasonParagraph (7) of Protocol Section 8.1.1.2.1.5, System Black Start Capability Qualification and Testing, requires Qualified Scheduling Entities (QSEs) who represent Black Start Resources to complete an ERCOT-provided report form for Black Start Resource availability tests. This NOGRR adds the form to the Nodal Operating Guide.
Created2012-06-13
Sections Affected
8I (new)
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds a Black Start Resource availability test form to the Nodal Operating Guide.
Action Log 4 milestones
-
Jun 13
OWGRecommended for Approval→ OWG IA Review
-
Jul 18
OWGRecommended for Approval→ ROS Consideration
-
Aug 16
ROSRecommended for Approval→ TAC Consideration
-
Sep 7
TACApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jun 13 '12 | OWG | Consensus to recommend approval of NOGRR097 as amended by the 5/30/12 Luminant Energy Company, LLC comments and as revised by OWG | |
| Jul 18 '12 | OWG | Consensus to endorse and forward the 6/13/12 OWG Report as revised by OWG and the Impact Analysis for NOGRR097 to ROS | |
| Sep 7 '12 | TAC | To approve NOGRR097 as recommended by ROS in the 8/16/12 ROS Report and as revised by TAC | Passed |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 097NOGRR-01 New Section 8I, Black Start Availability Test Form 0 | doc | May 25 '12 | Revision Request |
| 097NOGRR-02 Impact Analysis 052512 | doc | May 25 '12 | Staff Report |
| 097NOGRR-03 Luminant Energy Company, LLC 053012 | doc | May 30 '12 | Revision Request Comments |
| 097NOGRR-04 OWG Report 061312 | doc | Jun 18 '12 | Committee Report |
| 097NOGRR-05 OWG Report 071812 | doc | Jul 19 '12 | Committee Report |
| 097NOGRR-06 ROS Report 081612 | doc | Aug 16 '12 | Committee Report |
| 097NOGRR-07 TAC Report 090712 | doc | Sep 10 '12 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Sep 7 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Aug 16 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Jul 18 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Jun 13 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |