NOGRR #91 · Revision Request
NOGRR091 Criteria for the Selection of Operators
- ROS Jul 12 '12
- TAC Sep 7 '12
- BOARD —
- PUCT —
ReasonRemoves ambiguous wording, but retains important criteria specific for operators.
Created2012-05-16
Sections Affected
1.5.5
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds clarification to the criteria for the selection of operators in the ERCOT Region.
Timeline
- Apr 4
-
May 16
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Amended by the Apr 23 '12 CenterPoint Energy comments“In consensus to recommend approval of NOGRR091 as amended by the 4/23/12 CenterPoint Energy comments.” — Passed→ OWG review the IA
-
Jun 13
OWG Operations Working Group (OWG) MeetingOWG“In consensus to recommend approval of NOGRR096 as submitted.” — Passed→ ROS consideration
-
Jul 12
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval“To recommend approval of NOGRR091 as recommended by OWG in the 6/13/12 OWG Report.” — Passed→ TAC consideration
-
Sep 7
TAC Technical Advisory Committee (TAC) MeetingTACApproved“To approve NOGRR091 as recommended by ROS in the 7/12/12 ROS Report” — Passed
-
—