NOGRR #89 · Revision Request
NOGRR089 Clarification of Responsibilities for Black Start Resources and QSEs
- ROS Jun 14 '12
- TAC Jun 28 '12
- BOARD —
- PUCT —
ReasonThe local Black Start plan is developed by the appropriate TO and then is incorporated into the ERCOT Black Start Plan. The QSE provides a support role, as needed, during a Partial Blackout or a Blackout of the ERCOT System but may not be directly involved in the initial activities associated with a Black Start Resource when TOs and ERCOT are communicating directly with the Black Start Resource.
Created2012-01-30
Sections Affected
4.64.6.48E9.4.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) clarifies the responsibilities of the Black Start Resource and the Qualified Scheduling Entity (QSE) representing the Black Start Resource. It also clarifies language related to the Transmission Operator’s (TO’s) local Black Start plans and the QSE's Black Start procedures.
Timeline
- Dec 14
-
Jan 30
OWG Operations Working Group (OWG) MeetingOWGDeferred/Tabled“Consensus to table NOGRR089 for one month”→ OWG Language Consideration
-
Feb 15
OWG Operations Working Group (OWG) MeetingOWGDeferred/Tabled“Consensus to table for one month”→ OWG Consideration
-
Apr 18
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Amended by the Apr 3 '12 BSWG comments“Consensus to recommend approval of NOGRR089 as revised by the 4/3/12 BSWG comments”→ OWG IA Review
-
May 16
OWG Operations Working Group (OWG) MeetingOWGRecommended for Approval Forwarded → ROS“Consensus to endorse and forward the 4/18/12 OWG Report and Impact Analysis to ROS”→ ROS Consideration
-
Jun 14
ROS Reliability and Operations Subcommittee (ROS) MeetingROSRecommended for Approval“To recommend approval of NOGRR089 as recommended by OWG in the 5/16/12 OWG Report” — Passed→ TAC Consideration
-
Jun 28
TAC Technical Advisory Committee (TAC) MeetingTACApproved“To approve NOGRR089 as recommended by ROS in the 6/14/12 ROS Report” — Passed
-
—