NOGRR #88 · Revision Request
NOGRR088 Synchronization with NPRR424, Reactive Capability Testing Requirements for IRRs
ReasonTo synchronize the Nodal Operating Guides with NPRR424.
Created2012-01-30
Sections Affected
3.3.2.23.3.2.3
Summary
This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 424 which defines the reactive capability testing requirement for Intermittent Renewable Resources (IRRs).
Action Log 5 milestones
-
Jan 30
OWGRecommended for Approval→ OWG IA Review
-
Feb 15
OWGRecommended for Approval→ ROS Consideration
-
Mar 8
ROSRecommended for Approval→ TAC Consideration
-
Apr 5
TACDeferred/Tabled→ TAC Consideration
-
Jun 7
TACApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jan 30 '12 | OWG | Consensus to recommend approval of NOGRR088 as revised by OWG |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 088NOGRR-01 Sychronization with NPRR424 Reactive Capability Test | doc | Dec 12 '11 | Revision Request |
| 088NOGRR-02 Impact Analysis 121211 | doc | Dec 12 '11 | Staff Report |
| 088NOGRR-03 OWG Report 013012 | doc | Feb 1 '12 | Committee Report |
| 088NOGRR-04 OWG Report 021512 | doc | Feb 16 '12 | Committee Report |
| 088NOGRR-05 ROS Report 030812 | doc | Mar 26 '12 | Committee Report |
| 088NOGRR-06 TAC Report 040512 | doc | Apr 10 '12 | Committee Report |
| 088NOGRR-07 TAC Report 060712 | doc | Jun 11 '12 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 7 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Apr 5 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Mar 8 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Feb 15 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Jan 30 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |