NOGRR #80 · Revision Request
NOGRR080 Inadvertent Interchange and Inadvertent Energy Clarification
ReasonThe term "Inadvertent Interchange" as used in the North American Electric Reliability Corporation (NERC) Standards (i.e., BAL-006, Inadvertent Interchange) does not apply to the ERCOT interconnection because ERCOT is not synchronously connected to other interconnections. The term used in the ERCOT Region that describes the difference between scheduled and actual energy across the Direct Current Ties (DC Ties) is "inadvertent energy" as described in Protocol Section 6.5.4 and Section 3.8, Managing Daily Inadvertent Energy for the SPP DC Ties, of the Operating Procedure Manual, DC Tie Desk. This NOGRR modifies the language related to inadvertent energy to remain consistent with the Protocols, the Operating Procedure Manual, DC Tie Desk, NERC Standards and the equation used by ERCOT Independent System Operator (ISO) to calculate Area Control Area (ACE).
Created2011-10-19
Sections Affected
1.42.8.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) modifies language in Sections 1.4 and 2.8.1 related to inadvertent energy.
Action Log 4 milestones
-
Oct 19
OWGRecommended for Approval→ OWG for Impact Analysis review.
-
Nov 16
OWGRecommended for Approval→ ROS for consideration.
-
Jan 12
ROSRecommended for Approval→ TAC for consideration.
-
Feb 2
TACApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 080NOGRR-01 Inadvertent Interchange and Inadvertent Energy Clari | doc | Sep 21 '11 | Revision Request |
| 080NOGRR-02 OWG Report 101911 | doc | Nov 4 '11 | Committee Report |
| 080NOGRR-03 Impact Analysis 110411 | doc | Nov 4 '11 | Staff Report |
| 080NOGRR-04 OWG Report 111411 | doc | Nov 16 '11 | Committee Report |
| 080NOGRR-05 ROS Report 011212 | doc | Jan 13 '12 | Committee Report |
| 080NOGRR-06 TAC Report 020212 | doc | Feb 6 '12 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Feb 2 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Jan 12 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Oct 19 '11 | Operations Working Group (OWG) Meeting | OWG | Concluded |