NOGRR #77 · Revision Request

NOGRR077  Synchronization with NPRR379, EILS Dispatch Sequence and Performance Criteria Upgrades

Approved sponsor ERCOT posted 2011-07-05 ercot.com
ReasonTo synchronize the Nodal Operating Guides with NPRR379.
Created2011-07-20
Sections Affected
4.5.3.3 and 9.1.4
Summary
This Nodal Operating Guide Revision Request (NOGRR) synchronizes the Nodal Operating Guides with Nodal Protocol Revision Request (NPRR) 379, EILS Dispatch Sequence and Performance Criteria Upgrades, which provides ERCOT Operators with enhanced flexibility for managing grid conditions during an Energy Emergency Alert (EEA) by requiring dispatch of EILS prior to or in conjunction with dispatch of Load Resources providing Responsive Reserve (RRS) in EEA Level 2.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Jul 20 '11OWG Consensus to recommend approval of NOGRR077 as revised by OWG
Documents 10
NameTypePostedClassification
077NOGRR-01 Synchronization with NPRR379, EILS Dispatch Sequence doc Jul 5 '11 Revision Request
077NOGRR-02 Impact Analysis 070511 doc Jul 5 '11 Staff Report
077NOGRR-03 OWG Report 072011 doc Jul 25 '11 Committee Report
077NOGRR-04 Revised Impact Analysis 081011 doc Aug 10 '11 Staff Report
077NOGRR-05 OWG Report 081711 doc Aug 19 '11 Committee Report
077NOGRR-06 ERCOT Comments 090811 doc Sep 8 '11 Revision Request Comments
077NOGRR-07 ROS Report 091511 doc Sep 19 '11 Committee Report
077NOGRR-08 ROS Report 092911 doc Oct 4 '11 Committee Report
077NOGRR-09 ROS Email Vote 092911 xls Sep 29 '11 Revision Request Ballot
077NOGRR-09 TAC Report 100611 doc Oct 7 '11 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Oct 6 '11 TAC Meeting TAC Concluded
Sep 21 '11 Operations Working Group (OWG) Meeting OWG Concluded
Sep 15 '11 ROS Meeting ROS Concluded
Aug 17 '11 Operations Working Group (OWG) Meeting OWG Concluded
Jul 20 '11 Operations Working Group (OWG) Meeting OWG Concluded