NOGRR061 Posting Requirement for Hydro-Responsive Testing
ReasonPursuant to Protocol section 8.1.1.2, General Capacity Testing Requirements, hydro responsive tests occur on a seasonal basis not monthly.
Created2011-03-07
Sections Affected
9.4.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) changes the requirement for ERCOT to post a monthly report for hydro-responsive testing to a seasonal report, aligning the Nodal Operating Guides with the Protocols.
Action Log 4 milestones
-
Mar 7
OWGRecommended for Approval→ OWG for Impact Analysis review.
-
Apr 20
OWGRecommended for Approval→ ROS for consideration.
-
May 12
ROSRecommended for Approval→ TAC for consideration.
-
Jun 2
TACApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 061NOGRR-01 Posting Requirement for Hydro Responsive Testing 020 | doc | Feb 4 '11 | Revision Request |
| 061NOGRR-02 Impact Analysis 020411 | doc | Feb 4 '11 | Staff Report |
| 061NOGRR-03 OWG Report 030711 | doc | Mar 9 '11 | Committee Report |
| 061NOGRR-04 OWG Report 042011 | doc | Apr 22 '11 | Committee Report |
| 061NOGRR-05 ROS Report 051211 | doc | May 12 '11 | Committee Report |
| 061NOGRR-06 TAC Report 060211 | doc | Jun 6 '11 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 2 '11 | TAC Meeting | TAC | Concluded |
| May 18 '11 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| May 12 '11 | ROS Meeting | ROS | Concluded |
| Apr 20 '11 | OWG Meeting | OWG | Concluded |
| Mar 7 '11 | OWG Meeting | OWG | Concluded |