Summary
This Nodal Operating Guide Revision Request (NOGRR) replaces the term "Resource Plan" with the term"Current Operating Plan" in the instance where the change in terminology was not previously made.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
060NOGRR-01 Updating the Term Resource Plan to Current Operating doc Feb 1 '11 Revision Request
060NOGRR-02 OWG Report 030711 doc Mar 14 '11 Committee Report
060NOGRR-03 Impact Analysis 031411 doc Mar 14 '11 Staff Report
060NOGRR-04 OWG Report 042011 doc Apr 22 '11 Committee Report
060NOGRR-05 ROS Report 051211 doc May 16 '11 Committee Report
060NOGRR-06 TAC Report 060211 doc Jun 3 '11 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jun 2 '11 TAC Meeting TAC Concluded
May 18 '11 Operations Working Group (OWG) Meeting OWG Concluded
May 12 '11 ROS Meeting ROS Concluded
Apr 20 '11 OWG Meeting OWG Concluded
Mar 7 '11 OWG Meeting OWG Concluded