COPMGRR #29 · Revision Request

COPMGRR029  Clarifying Reporting Requirements for Unregistered Distributed Generation

Approved sponsor Jim Lee on behalf of COPS Communications Working Group (CCWG) posted 2011-10-26 ercot.com
  1. COPS Jan 10 '12
  2. TAC Feb 2 '12
  3. BOARD
  4. PUCT
ReasonThe reason for this revision is to provide market clarity on registration requirements for DG greater than 50 kW and less than or equal to one MW.
Created2011-11-17
Sections Affected
10.3.110.3.3
Summary
This Commercial Operations Market Guide Revision Request (COPMGRR) clarifies the requirements for Non-Opt-In Entities and ERCOT for reporting unregistered Distributed Generation (DG).
Timeline