COPMGRR #28 · Revision Request
COPMGRR028 Synchronization with NPRR374, Modification of SCR Process and Urgency Requirements
- COPS Dec 6 '11
- TAC Jan 5 '12
- BOARD —
- PUCT —
ReasonAlignment with the Nodal Protocols by removing the rapid implementation requirement in the definition of Urgency.
Created2011-10-27
Sections Affected
4.6
Summary
This Commercial Operations Market Guide Revision Request (COPMGRR) aligns the Commercial Operations Market Guide (COPMG) with changes proposed by Nodal Protocol Revision Request (NPRR) 374, Modification of SCR Process and Urgency Requirements, which modified the requirements for Urgency.
Timeline
- Oct 7
-
Oct 27
CCWG COPS Communication Working Group (CCWG) MeetingCCWGRecommended for Approval“CCWG was in consensus to recommend approval of COPMGRR028 as submitted.” — Passed→ CCWG review the Impact Analysis
-
Nov 17
CCWG COPS Communication Working Group (CCWG) MeetingCCWGRecommended for Approval Forwarded → COPS“Consensus to endorse and forward the 10/27/11 CCWG Report and the Impact Analysis for COPMGRR028 to COPS.” — Passed→ COPS consideration
-
Dec 6
COPS COPS MeetingCOPSRecommended for Approval“To recommend approval of COPMGRR028 as recommended by CCWG in the 11/17/11 CCWG Report.” — Passed→ TAC consideration
-
Jan 5
TAC Technical Advisory Committee (TAC) MeetingTACApproved“To approve COPMGRR028 as recommended by COPS in the 12/6/11 COPS Report.” — Passed
-
—