Revision Requests On The Agenda
Agenda 18 items
- 1. Antitrust Admonition — Koellner · 12:30 p.m.
- 2. Roster & calendar review/update — Koellner
- 3. Review & approval of minutes from previous meeting Action item review Recap of activity since July meeting — Koellner
- 4. Relay Misoperation and TADS data update from TRE-Penney Changes to TRE Misoperation Reporting Procedure and Template — Penney
- 5. Standards activity & update PRC-005, PRC-023, PRC-027, FERC Orders 754 & 758, etc — Francis
- 6. Annual ERCOT DME submittal market notice — Burford
- 7. FERC Order 754 how are folks handling their responses? — Koellner
- 8. Updates to "Examples of applying k-Factor' document — ALL
- 9. NERC Cause Analysis document/training — Datta - Barua
- 10. Interconnect study guidelines-review draft document from ERCOT — Dixit
- 11. Short circuit (SC) case building Establish draft schedule for next year’s case building Upgrading to PSSE v33.3 prior to next case build Integrating new 900+ area numbers for resource owned equipment Using RARF models and changing bus number to match SSWG CREZ 'max export' short circuit case-integration into ERCOT cases Capture any revisions to SPWG SC case building procedure Wind turbine short circuit modeling PGRR018 — ALL
- 12. Review draft NOGRR — Koellner
- 13. Relay remote access - best practices, challenges, etc. — Mattei
- 14. Lessons learned/event review- 345kV event model validation Using event data for generator model validation — ALL Rose/Rajagopalan
- 15. Review items requiring submittal before the next SPWG meeting — Koellner
- Next SPWG Meeting: Host: ERCOT Date: February 2013 (date TBD) Location: 7620 Metro Center Dr., Austin, TX
- Action Items/Notes