Meeting · RIWG
Resource Integration Workshop
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room 206
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 13 items
- 1. Anti-trust Admonition — ERCOT · 9:30 – 9:35 a.m.
- Recap of the September 28 RI workshop
-
2.
GINR Topics
— ERCOT/Teixeira
· 9:35 – 9:50 a.m.
- 2.ResourceIntegrationWorkshop GINR Topics 10292018 · Staff Report
-
3.
Dynamic Model Template Implementation
— ERCOT/Khan
· 9:50 – 10:20 a.m.
- 3.Dynamic Templates RI Workshop · Stakeholder Presentation
-
4.
ERCOT Screening Study Process
— ERCOT/Hayden
· 10:20 – 10:50 a.m.
- 4.Appendix A Case Changes · Staff Report
- 4.Appendix B Contingency Analysis · Staff Report
- 4.Appendix C Transfer Analysis · Staff Report
- 4.Screening Study Process final · Staff Report
-
5.
RIOO FIS Data Requirements
— ERCOT/Reich
· 10:50 – 11:30 a.m.
- 5.Required Data for FIS SSR for TSP Feedback Conventional Generation · Forms and Templates
- 5.Required Data for FIS SSR for TSP Feedback Solar · Forms and Templates
- Lunch · 11:30 a.m. – 1:00 p.m
- *** TSP Only Afternoon Session *** — Webex Info sent to TO List
- 6. RIOO Interconnection Services Update — ERCOT/Siebold · 1:00 – 2:00 p.m.
- 7. Other Topics — All · 2:00 – 2:30 p.m.
- Cases for Stability Studies
- FIS Re-study Requirement
- 8. Adjourn — All · 2:30 p.m.