Meeting · RPG
RPG Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Rooms A and B
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 15 items
- 1. Antitrust Admonition · 9:30 a.m.
- 2. Miscellaneous Updates — ERCOT · 9:35 a.m.
- 3. EIR Status Update – Childress Area Transmission Improvement Project — ERCOT · 9:40 a.m.
- 4. EIR Status Update – Combined CPS Energy Reactive Power Planning Project & CPS Energy Helotes 345/138-kV Switching Station and Autotransformer Addition at Eastside Switching Station Project — ERCOT · 9:50 a.m.
- 5. EIR Status Update – Ammonia Plant Load Project — ERCOT · 10:00 a.m.
- 6. EIR Status Update – Nueces Green Ammonia Load Interconnection Project — ERCOT · 10:10 a.m.
- 7. EIR Status Update – Muscovy and Voss Lake 345/138-kV Project — ERCOT · 10:20 a.m.
- 8. EIR Status Update – Connell 345/138-kV Switch and Connell to Rockhound 345-kV Double-Circuit Line Project — ERCOT · 10:30 a.m.
- 9. EIR Status Update – P.H. Robinson to W.A. Parish 345-kV Hardening Project — ERCOT · 10:40 a.m.
- 10. EIR Status Update – Texas 765-kV-STEP Eastern Backbone Project — ERCOT · 11:00 a.m.
- 11. EIR Status Update – Drill Hole to Sand Lake to Solstice 765-kV Line Project — ERCOT · 11:10 a.m.
- 12. Skyview 345/138-kV Switch Project Overview — Oncor · 11:20 a.m.
- 13. ERCOT Independent Review Scope: Skyview 345/138-kV Switch Project — ERCOT · 11:30 a.m.
- 14. 2025 RTP Economic Analysis Update — ERCOT · 11:40 a.m.
- 15. Adjourn — ERCOT · 12:00 p.m.