Meeting · RPG
RPG Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Rooms A and B
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 20 items
- 1. Antitrust Admonition · 9:30 a.m.
- 2. Miscellaneous Updates — ERCOT · 9:35 a.m.
- 3. 2025 Regional Transmission Plan (RTP) Economic Study: Stability Interface Limits — ERCOT · 9:40 a.m.
- 4. EIR Status Update – Baytown Area Load Addition Project — ERCOT · 10:00 a.m.
- 5. EIR Status Update – Connell 345/138-kV Switch and Connell to Rockhound 345-kV Double-Circuit Line Project — ERCOT · 10:10 a.m.
- 6. EIR Status Update – Muscovy and Voss Lake 345/138-kV Project — ERCOT · 10:20 a.m.
- 7. EIR Status Update – BEC Hamilton County Conversion Project — ERCOT · 10:30 a.m.
- 8. EIR Status Update – Texas A&M University System RELLIS Campus Reliability Project — ERCOT · 10:40 a.m.
- 9. EIR Status Update – Southern DFW Load Interconnection and General Grid Strengthening Project — ERCOT · 10:50 a.m.
- 10. Reactive Power Planning Project Overview — CPS Energy · 11:00 a.m.
-
11.
Helotes 345/138-kV Switching Station & Autotransformer Addition at Eastside Switching Station Project Overview
— CPS Energy
· 11:10 a.m.
- CPSE Helotes Switching Station and Autotransformer Addition at Eastside Switching Station · Stakeholder Presentation
-
12.
ERCOT Independent Review Combined Scope: Reactive Power Planning Project & Helotes 345/138-kV Switching Station and Autotransformer Addition at Eastside Switching Station Project
— ERCOT
· 11:20 a.m.
- CPSE Helotes Switching Station and Autotransformer Addition at Eastside Switching Station · Stakeholder Presentation
-
13.
Ammonia Plant Load Project Overview
— STEC
· 11:30 a.m.
- STEC_FirstAmmonia_Final_25RPG012 · Stakeholder Presentation
-
14.
ERCOT Independent Review Scope: Ammonia Plant Load Project
— ERCOT
· 11:40 a.m.
- STEC_FirstAmmonia_Final_25RPG012 · Stakeholder Presentation
-
15.
Nueces Green Ammonia Load Interconnection Project Overview
— STEC
· 11:50 a.m.
- STEC_NuecesGeenAmmonia_Final_25RPG016 · Stakeholder Presentation
-
16.
ERCOT Independent Review Scope: Nueces Green Ammonia Load Interconnection Project
— ERCOT
· 12:00 p.m.
- STEC_NuecesGeenAmmonia_Final_25RPG016 · Stakeholder Presentation
- 17. Childress Area Transmission Improvement Project Overview — AEPSC · 12:10 p.m.
- 18. ERCOT Independent Review Scope: Childress Area Transmission Improvement Project — ERCOT · 12:20 p.m.
- 19. 2025 RTP Assumptions — ERCOT · 12:30 p.m.
- 20. Adjourn — ERCOT · 1:00 p.m.