Meeting · WMWG
WMWG Meeting by Webex Only
VirtualWebEx / Teams
Dial-in877-668-4493
Revision Requests On The Agenda
Agenda 28 items
- 1. Antitrust Admonition — D. Detelich · 9:30 AM
- 2. Increase the minimum quantities of Responsive Reserve Service and Non-Spinning Reserve Service — D. Detelich
- Topics for this meeting will be from the document For Evaluation at WMWG July 7, 2021 WMS
- Not all the topics can be fully evaluated in this meeting
- 3. Energy Pricing Impacts — ERCOT
-
Should offline NSRS be deployed before SCED could get to market based offers from QSGR not providing NSRS?
- Changes to address market impacts of AS deployments · Stakeholder Presentation
-
Should Online reserves be below certain level in addition to PRC <3200 before offline NSRS is deployed?
- Changes to address market impacts of AS deployments · Stakeholder Presentation
-
Should offline NSRS be deployed in chunks?
- Changes to address market impacts of AS deployments · Stakeholder Presentation
-
Should $75/MWh offer floor language for online reserves be extended to offline reserves?
- Changes to address market impacts of AS deployments · Stakeholder Presentation
-
Should 0-lsl of offline NSRS be relaxed in pricing run?
- Changes to address market impacts of AS deployments · Stakeholder Presentation
- 4. ERCOT Reports — ERCOT
-
Monthly Review – Questions on Monthly Reports
- Intra Hour IRR Forecast Accuracy Jun.2021 · Staff Report
- Market Update June 2021 WMWG · Staff Report
- June 2021 WMWG GREDP Summary · Staff Report
- SolarPowerForecastMonthly Jun2021 WMWG.XLSX · Staff Report
- WindPowerForecastMonthly Jun2021 WMWG.XLSX · Staff Report
-
Review accuracy of forecast variability that is used to determine the additional AS Requirement
- Intra Hour IRR Forecast Accuracy Jun.2021 · Staff Report
- SolarPowerForecastMonthly Jun2021 WMWG.XLSX · Staff Report
- WindPowerForecastMonthly Jun2021 WMWG.XLSX · Staff Report
- How is the determination made?
- What should be reviewed in a monthly report?
- 5. Review Impact to Retailers on procuring Additional Reserves — D. Detelich
- Should self-arrangements be opened up further to increase liquidity & enable hedging?
- Provide update on aggregate capacity qualified to provide AS — N. Mago
- 6. Review the Impact to Cycling Resource before it is really needed in Peak Summer — D. Detelich
- Reliability has been good the last few summers in part because cycling of units has been reduced
- This summer SARA has a reduced number of Typical Forced Outages
- 7. Should advance RUCing be delayed based on start time to give enough time for ERCOT to have capacity in time and at the same time allow Market to respond to Self-Commit? — ERCOT
- 8. Address concerns raised for NPRR1080 – July WMWG — D. Detelich
-
Related to payment for resources that are assigned AS in RT
— ERCOT
- Issues related to NPRR1080 on Capping AS Prices 071221 · Stakeholder Presentation
- AS Assignment WMWG v2 · Stakeholder Presentation
-
Related to procurement for AS in reference to AS penalty factor
- Issues related to NPRR1080 on Capping AS Prices 071221 · Stakeholder Presentation
- 9. Other Business — D. Detelich
- Adjourn — D. Detelich
- Future Meetings – August 23, 2021