Meeting · LFLTF
LFLTF Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Rooms A, B and C
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 18 items
- 1. Welcome and Antitrust Admonition — ERCOT – Bill Blevins · 9:30 a.m.
- 2. Interconnection and Planning Issues — ERCOT – Bill Blevins · 9:40 a.m.
- Definitions and criteria
- Interconnection Process
- 3. Operations Issues · 11:00 a.m.
- Manual Loadshed — Oncor
-
UFLS
— AEP
- LFL-31 Consider impacts to Transmission Operator UFLS obligations_06272022v2 · Stakeholder Presentation
-
Outage Coordination
— CNP
- LFLTF Issue 35 Outage Scheduling · Stakeholder Presentation
- GTC/GTLs — ERCOT
- Break · 12:30 p.m.
- 4. Market Issues · 1:30 p.m.
-
Demand Response CLR Nodal settlement
— ERCOT – Sai Moorty
- LFLTF 06292022 Demand Response CLR Nodal Settlement - Proposed NPRR v8 · Revision Request
- LFL11 · Stakeholder Presentation
- LFLs in DAM — Eric Goff
- LFLs in RUC — Eric Goff
-
Mitigating Price Oscillations in SCED
— Clayton Greer
- Reduced SCED Time - djm - cag · Stakeholder Presentation
-
LFL’s in CCT and Real-Time Mitigation Process
— Dave Maggio
- LFL15 and 21 - Constraint Competitiveness Test Process · Staff Report
- 5. Next LFLTF Meeting · 3:30 p.m.
- Adjourn — ERCOT – Bill Blevins · 4:00 p.m.
Documents 6
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| LFL Ops V2 6-26-22 Oncor | Stakeholder Presentation | pptx | Jun 28 '22 |
| LFL18 | Stakeholder Presentation | docx | Jun 29 '22 |
| LFL26 | Stakeholder Presentation | docx | Jun 29 '22 |
| LFL28 | Revision Request Comments | docx | Jun 29 '22 |
| LFL33 | Revision Request | docx | Jun 29 '22 |
| LFL37 | Revision Request | docx | Jun 29 '22 |