- 1. Antitrust Admonition
- 2. Goal(s) of the Task Force
- 2. Review Inventory of CC Resource Asset Registration
- 3. Procurement Discussion of ERCOT?s capacity procurement processes (automated and manual) under EMMS Release 4.0 Discussion of CC Resource operational capabilities (i.e., ability to operate steam generator only, ability to operate combustion turbine(s) only)
- 4. Settlement What is represented by the Generic Startup and Minimum Energy Costs for Combined Cycle Resources in 6.8.2.1(4) and (5)? When does a unit commitment payment for local congestion occur under 6.8.1.11(4) vs. 6.8.2.2(5)? What is the purpose of the clawback during the ramp in Section 6.8.2.2(5)? Why does the startup payment in 6.8.2.2(5) have a clawback for the ramp period whereas the startup payment in 6.8.1.11(4) does not have such a clawback? Example shadow calculation of CC OOMC payment ? Discussion What is the proper LSL to represent for CC units in the DA when the units are shown as offline and available? Is there a consistent approach that can be adopted?
- 5. Summary and Next Steps
Documents 1
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| CCRPRSTF Notes_032006 | Meeting Minutes | doc | Apr 10 '06 |