Meeting · RPG
RPG Meeting by Webex Only
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 8 items
- 1. Antitrust Admonition
- 2. Miscellaneous Updates — (5min, ERCOT)
- 3. Study for Remaining LP&L Load Transfer — (20min, ERCOT)
- 4. Roanoke Area Upgrades — (20min, Oncor)
- 5. ERCOT Independent Review Scope: Roanoke Area Upgrades — (20min, ERCOT)
-
6.
2022 RTP Known Outages
— (20min, ERCOT)
- 2022 Regional Transmission Plan Scope and Process - Version 2.0 - Redline · Official Guides and Manuals
-
7.
2022 RTP Assumptions Update
— (20min, ERCOT)
- 2022 Regional Transmission Plan Scope and Process - Version 2.0 - Redline · Official Guides and Manuals
-
8.
2022 RTP Load Review Update
— (20min, ERCOT)
- 2022 Regional Transmission Plan Scope and Process - Version 2.0 - Redline · Official Guides and Manuals
Documents 7
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| 2022 RTP: TPL-001-5.1 Known Outages Presentation | Mar 9 '22 | ||
| 2022 RTP Assumptions Update Presentation | Mar 15 '22 | ||
| 2022 RTP Load Review Update | Mar 15 '22 | ||
| 2022 Regional Transmission Plan Scope and Process - Version 2.0 - Clean | Mar 11 '22 | ||
| Lubbock Power & Light (LP&L) Remaining Load Integration Study Scope | Mar 10 '22 | ||
| Oncor – Roanoke Area Upgrades – ERCOT Independent Review Scope | Mar 11 '22 | ||
| Roanoke Area Upgrades Overview | Mar 11 '22 |