Meeting · SPWG
SPWG Meeting by WebEx Only
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 33 items
- 1. Antitrust Admonition — J. Karlik
- 2. Roster & Calendar Review/Update — J. Karlik
- Pass Around Membership Roster & Sign-in Sheet
- Pass Around Internal SPWG Coordination Roster
- Self-introductions Around the Table and on the Phone
- Welcome New Members
- Review SPWG Calendar
- 3. Review and Approval of Minutes from Previous Meeting — J. Karlik
- 4. Action Item Review and Status Update — J. Karlik
- 5. Updates from TRE — D. Penney
- Year-end Mis-op Summary (Tentative)
- Mis-op Report: Clarification of Definitions for ROS
- 6. NERC PRC Standard Activities Report to ERCOT SPWG — G. Hargrave/A. Klusman
- 7. ERCOT Activity & Updates — ERCOT
- 8. The Impact of Inverter-Based Resources on the ERCOT Grid Protection Discussion Protection Discussion — F. Huang/SPWG Members
- Background Discussion
- TSP Response
- Inverter-Based Resource Short Circuit Modeling
- System Protection Best Practices
- Facility Interconnection Request
- 9. Generator Interconnects and DME FR/SER Requirements — B. Burford
- 10. Implementation of NPRR-953 Discussion — ERCOT/SPWG Members
- Review Requirements
- Remaining Items to Address
- 11. Implementation of PRC-027 Discussion — J. Karlik
- Review Requirements
- Discuss Approaches to Comply with R2
- 12. Interesting Event Reviews — Volunteers
- 13. Other Items — SPWG Members
- Open Discussion
- 14. Review of Items Requiring Submittal Before Next SPWG Meeting — V. Roberts
- 15. Adjourn
- Next Meeting: July 22-23, 2020
Documents 1
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| ERCOT SPWG Agenda 2020 03 04 r00 | Meeting Agenda | docx | Feb 25 '20 |