Meeting · RSC
Reliability Standards Committee Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room 168
Agenda 8 items
-
1.
Welcome Antitrust Admonition Approval of 02/04/09 minutes ** Vote
— R. Keetch
· 9:30 a.m.
- 01-Draft_RSC_Meeting_Minutes_2009-02-04 · Meeting Minutes
-
2.
Presentation of BAL-001-TRE-01 SAR-003 SDT Draft Standard Discussion Post for Comment **Vote
— S. Niemeyer
· 9:40 a.m.
- 02a-BAL-001-TRE-1_2.27.09_SDT_clean · Official Guides and Manuals
- 02b-Frequency_Response_data_report_for_Single_BA_Interconnection · Staff Report
- 02c-Frequency Response and Droop Calculator for Resources · Forms and Templates
- 02d-Droop_Calc_zero_Hz_db_4%_droop_CT_and_ST · Forms and Templates
- 02e-Droop Calc 0.0166 Hz db 5% droop Steam Unit · Forms and Templates
- 02f-Draft of Compliance Implementation Schedule DRAFT 1 · Project Documents
- 02g-SAR-003-TRE-001Report to RSC 20090304 · Committee Report
-
3.
NERC Project 2006-03 System Restoration and Blackstart Revision of EOP-005, 006, 007, 009 Presentation and Discussion Question and Answer
— R. Terrill
· 10:15 a.m.
- 03a-System Restoration and Blackstart Texas RE presentation · Stakeholder Presentation
- 03b-SRB SDT_EOP_005_2_20090302 DRAFT clean · Official Guides and Manuals
- 03c-SRB SDT_EOP_006_2_20090302 DRAFT clean · Official Guides and Manuals
-
4.
SAR-002 UFLS SDT Update Presentation
— B. Bartos
· 11:15 a.m.
- 04-Mar 2009_TRE SAR002_Status Report_BDB · Staff Report
- 5. Texas RE Board Update SAR-001 Provision to Give ERCOT ¼ Vote - Approved — J. James · 11:30 a.m.
-
6.
LSE Joint Registration Update Texas RE Move to New Location-Map RSM Presentation to TAC March 5 RSC Top 10 Projects List SDT Participation Requirements-Discussion
— J. James
· 11:35 a.m.
- 06-RSM Report to RSC · Committee Report
- 7. Adjourn · 12:00 p.m.
- Next Meeting April 1, 2009 Room 206 B, Austin Met Center
Documents 1
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| RSC_Meeting_Minutes_2009-03-04-Approved | Meeting Minutes | doc | May 8 '09 |