Meeting · RPG
RPG Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 MET Boardrooms A and B
VirtualWebEx / Teams
Dial-in877-668-4493
Agenda 13 items
- 1. Antitrust Admonition · 9:30 a.m.
- 2. Miscellaneous Updates — ERCOT · 9:35 a.m.
- 3. EIR Status Update – Paris Switch to Monticello Switch 345-kV Line Rebuild Project — ERCOT · 9:40 a.m.
-
4.
EIR Status Update – Nueces Green Ammonia Load Interconnection Project
— ERCOT
· 9:50 a.m.
- 4_EIR_STEC_Nueces_Green_Ammonia_Project_Status_Update_RPG_February_2026_FINAL · Project Documents
- 5. EIR Status Update – Combined CPS Energy Reactive Power Planning Project & CPS Energy Helotes 345/138-kV Switching Station and Autotransformer Addition at Eastside Switching Station Project — ERCOT · 10:00 a.m.
-
6.
Medina County Large Load Additions Project Overview
— STEC
· 10:10 a.m.
- 6_STEC_Medina County Large Load _RPG_final · Stakeholder Presentation
-
7.
ERCOT Independent Review Scope: Medina County Large Load Additions Project
— ERCOT
· 10:20 a.m.
- 7_EIR - STEC Medina County Large Load Project_SCOPE_Feb2026_RPG · Project Documents
-
8.
ERCOT Independent Review Updated Scope – Large Load Additions Project
— ERCOT
· 10:30 a.m.
- 8_EIR - CPS Energy Large Load Additions Project_Updated_SCOPF_Feb2026_RPG · Project Documents
-
9.
ERCOT Independent Review Scope: Combined Oncor Set 1 North & Central Texas Reliability Project & Oncor Set 2 North & Central Texas Reliability Project
— ERCOT
· 10:40 a.m.
- 9_EIR - Oncor - Combined Set 1 and Set 2 North and Central Texas Reliability Project - Scope - RPG Feb 2026 · Stakeholder Presentation
- 10. ERCOT Independent Review Scope: Combined Oncor Set 1 North Central & South Central Texas Reliability Project & Oncor Set 2 North Central & South Central Texas Reliability Project — ERCOT · 10:50 a.m.
- 11. ERCOT Independent Review Scope: Oncor and Lone Star Navarro and Ellis Area Reliability Project — ERCOT · 11:00 a.m.
-
12.
ERCOT Independent Review Scope: Southeast Brownsville Large Load Transmission System Improvements Project
— ERCOT
· 11:10 a.m.
- 12_EIR_STEC_Brownsville_Project_Scope_RPG_February_2026_FINAL · Project Documents
- 13. Adjourn — ERCOT · 11:20 a.m.